Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for April 10 - 14
 
The following construction deliveries are scheduled for April 10 - 14 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (15- 20 trucks) of ballast material at the layup yard.

WHEN: Monday – Friday between the hours of 7:00 a.m. to 5:00 p.m.

HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt.
606 to the project site.
-----------------------------------------------------------------------------------------
WHAT: Turnout delivery (2-3 trucks) for installation in the yard lead track.

WHEN: Thursday and Friday between the hours of 7:00 a.m. to 12:00 p.m.

HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/ Old Ox
Rd, and will have to turn around at Mercure Circle to make the right into the
jobsite.
-----------------------------------------------------------------------------------------
WHAT: Concrete delivery (8 trucks) for installation at the Service and Inspection
Building (approximately 80 cubic yards), including a 36m Pump Truck.

WHEN: Thursday and Friday between the hours of 6:00 a.m. to 12:00 p.m.

HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
-----------------------------------------------------------------------------------------
WHAT: Precast Panel Delivery (10 Trucks) in 45 minute increments for installation at
the Service and Inspection Building.

WHEN: Monday - Friday between the hours of 7:00 a.m. to 2:00 p.m.

HOW: Trucks will travel from Winchester VA, East on rte 7, South on 28, and West
along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure
Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Structural Steel Delivery (2-3 Trucks) for installation in the Service and
Inspection Building.

WHEN: Monday- Friday between the hours of 6:00 a.m. – 12:00 p.m.

HOW: Trucks will be coming from Tennessee, traveling North on Old Ox Rd/Rt. 606
from US 50.
-----------------------------------------------------------------------------------------
WHAT: Joist and deck delivery (2 trucks) for installation at the Service and Inspection
Building.

WHEN: Monday between the hours of 7:00 a.m. to 5:00 p.m.
 
HOW: Trucks will travel from South Carolina, North on 95, West on the Dulles Toll
Road, West along Old Ox Rd/Rt. 606, turning around at Mercure Circle to turn
right into the project site.
 
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.