Concrete and Gravel Deliveries for Feb. 13 - 17

  
February 10, 2017 
 
CONTACT: Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
 
 
 
Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for Feb. 13 - 17
 
The following construction deliveries are scheduled for Feb. 13 - 17 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (20-30 trucks) of sub ballast material at the layup yard.

WHEN: Monday – Wednesday between the hours of 7:30 a.m. to 5:00 p.m.

HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt.
606 to the project site.
-----------------------------------------------------------------------------------------
WHAT: Stone delivery (15 trucks) of ballast material at the layup yard.

WHEN: Monday – Friday between the hours of 7:00 a.m. to 5:00 p.m.

HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt.
606 to the project site.
-----------------------------------------------------------------------------------------
WHAT: Turnout and Switch Ties delivery (10 trucks) for installation in the layup yard.

WHEN: Wednesday between the hours of 7:00 a.m. to 12:00 p.m.

HOW: Trucks will travel from Reading, PA, West on 267, South on Rte 606/ Old Ox
Rd, and will have to turn around at Mercure Circle to make the right into the
jobsite.
-----------------------------------------------------------------------------------------
WHAT: Concrete Ties delivery (5 trucks) for installation in the layup yard.

WHEN: Monday - Friday between the hours of 6:00 a.m. to 12:00 p.m.

HOW: Trucks will travel from Delaware, West on 267, South on Rte 606/ Old Ox Rd,
and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Rebar delivery (3 trucks) for installation in the Service & Inspection Building,
and the Train Wash Facility.

WHEN: Monday between the hours of 6:00 a.m. to 10:00 a.m.

HOW: Trucks will travel from the Trowbridge plant, West on Rte 606/ Old Ox Rd, and
will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Crane delivery for use at the Maintenance of Way Building.

WHEN: Monday between the hours of 6:00 a.m. to 10:00 a.m
 
HOW: Trucks will travel from Tennessee, coming from Rte 50, North on Old Ox Rd/Rt.
606 to the project site.
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.