Skip to main content
Silver Line on Track

Concrete and Gravel Deliveries for Jan. 16 - 20

  
January 13, 2017 
 
CONTACT: Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
 
 
 
Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for Jan. 16 - 20
 
The following construction deliveries are scheduled for Jan. 16 - 20 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Concrete delivery (5 trucks) for installation at the Transportation & Police Building Flow Fill (approximately 48 cubic yards).
 
WHEN: Monday between the hours of 9:00 a.m. to 11:00 a.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. 
 
 
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.