Skip to main content
Silver Line on Track

Concrete and Gravel Deliveries Scheduled Along Old Ox Rd/Route 606 for Sept. 26 - 30

  
September 24, 2016 
 
CONTACT: Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
 
Concrete and Gravel Deliveries Scheduled along Old Ox Road/Route 606 for Sept. 26 - 30
 
The following construction deliveries are scheduled for Sept. 26 - 30 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Concrete delivery (7 - 10 trucks/day) and concrete pump truck for installation of Service Inspection Building basement walls.
 
WHEN: Wednesday, Sept. 28, and Friday, Sept. 30, from 10 a.m. to 3 p.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
 
----------------------------------------
 
WHAT: Concrete delivery (9 - 12 trucks/day) and concrete pump truck for installation of Service Inspection Building hoist pit walls.
 
WHEN: Monday, Tuesday and Thursday, from 7 a.m. to 12 p.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
----------------------------------------

WHAT: Import gravel from off-site location. Approximately 25 truckloads of gravel will be delivered to project site daily for the construction of the retaining wall. The material will be used for sub-base and backfill material.

 
WHEN: Monday - Friday from 7 a.m. to 4 p.m.
 
HOW: Trucks will travel to and from the project site via Old Ox Road/Rt. 606.
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.