The following construction deliveries are scheduled for Sept. 12 - 16, 2016 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Concrete delivery (7-10 trucks/day) and concrete pump truck for installation of Service and Inspection Building walls and hoist pit walls.
 
WHEN: Monday - Friday from 6:30 a.m. to 2 p.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
 
----------------------------------------
 
WHAT: Concrete delivery (5-7 trucks/day) and concrete pump truck for installation of Austin Sand Filter walls.
 
WHEN: Monday, Sept. 12, and Friday, Sept. 16, from 5:30 a.m. to 1 p.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site.

----------------------------------------

WHAT: Import gravel from off-site location. Approximately 25 truckloads of gravel will be delivered to project site daily for the construction of the retaining wall. The material will be used for subbase and backfill material.

 
WHEN: Monday - Friday from 7 a.m. to 4 p.m.
 
HOW: Trucks will travel to and from the project site via Old Ox Road (Rt. 606).
 
<><><><><> 
 
A 24/7 Hotline is available for Phase 2 Rail Yard construction-related issues: 952-939-6690.  For general project information: www.dullesmetro.com or 703-572-0506.