The following construction deliveries are scheduled for Dec. 4 - 9 (Monday - Saturday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (15 trucks) of ballast material at the layup yard.
 
WHEN: Monday - Friday between the hours of 7 a.m. to 5 p.m. 
 
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Rte 606/Old Ox Rd to the project site.  
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (6 trucks) for installation in the Track including a 36m truck.
 
WHEN: Monday between the hours of 9 a.m. to 12 p.m.  
 
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (20 trucks) for installation in the Service and Inspection Building Slab on Grade including a 47z truck.
 
WHEN: Tuesday between the hours of 4 a.m. to 12 p.m.  
 
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------

 

WHAT: Concrete delivery (10 trucks) for installation in the TPSS Slab on Grade including a 36m truck.

 
WHEN: Tuesday between the hours of 5 a.m. to 10 a.m.  
 
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (20 trucks) for installation in the Maintenance of Way Slab on Grade including a 31z truck.
 
WHEN: Wednesday between the hours of 4 a.m. to 11 a.m.  
 
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (32 trucks) for installation in the Warehouse Building Slab on Grade including a 31z truck.
 
WHEN: Thursday between the hours of 4 a.m. to 1 p.m.  
 
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (6 trucks) for installation in the Track including a 36m truck.
 
WHEN: Friday between the hours of 4 a.m. to 7 a.m.  
 
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.