Concrete Delivery Schedule for Jan. 14 - 18
  
 
 
The following construction deliveries are scheduled for Jan. 14 - 18 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below: 
 
 
 
<><><><><> 
 
WHAT: Formwork for Salt Dome (1 truck)
 
WHEN: Tuesday between the hours of 10 a.m. to 12 p.m.
 
HOW: Trucks will travel west along Old Ox Road/Route 606 to the project site.
 
---------------------------------------------------------------------------------------------------------------------------------------
 
WHAT: Miscellaneous equipment (Mobile Rail Car Mover) delivery (1 truck)
 
WHEN: Wednesday between the hours of 8 a.m. to 10 a.m.
 
HOW: Trucks will travel west along Old Ox Road/Route 606 to the project site.
 
--------------------------------------------------------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (4 trucks)
 
WHEN: Wednesday between the hours of 10 a.m. to 12 p.m.
 
HOW: Trucks will travel west along Old Ox Road/Route 606 to the project site.
 
--------------------------------------------------------------------------------------------------------------------------------------
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.