Concrete Delivery Schedule for July 17 – 21

July 14,  2017
 
CONTACT:     Marcia McAllister
      T: 703-572-0506
               C: 571-730-9117
               Marcia.McAllister@dullesmetro.com
 
Concrete Delivery Schedule for July 17 - 21
 
The following construction deliveries are scheduled for July 17 - 21 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Stone delivery (25 trucks) of ballast material at the layup yard.
 
WHEN: Monday - Friday between the hours of 7 a.m. to 5 p.m. 
 
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Old Ox Rd/Rt. 606 to the project site.  
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (15 trucks) for installation at the Service and Inspection Building Slab on Grade, sequence 2.
 
WHEN: Wednesday between the hours of 3 a.m. to 6 a.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. 
-----------------------------------------------------------------------------------------
 
WHAT: Concrete delivery (11 trucks) for installation at the Site Approach Slab.
 
WHEN: Tuesday between the hours of 6 a.m. to 9 a.m. 
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. 
-----------------------------------------------------------------------------------------
 
WHAT: Precast Panel delivery (16 trucks) in 45 minute increments for installation at the Maintenance of Way Building.
 
WHEN: Thursday between the hours of 7 a.m. to 2 p.m. 
 
HOW: Trucks will travel from Winchester VA, East on Rte 7, South on 28, and West along Old Ox Rd/Rt. 606 to the project site, making the U-Turn at Mercure Circle to make the right into the jobsite. 
-----------------------------------------------------------------------------------------
 
WHAT: Concrete ties delivery (4 trucks) for installation in the yard lead track.
 
WHEN: Monday - Friday between the hours of 7 a.m. to 12 p.m.  
 
HOW: Trucks will  travel from Reading, PA, West on 267, South on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
 
WHAT: Rebar delivery (1 truck) for installation in the Maintenance of Way Building and Transportation and Police Building.
 
WHEN: Wednesday - Friday between the hours of 6 a.m. to 10 a.m.
 
HOW: Trucks will  travel from the Trowbridge plant, West on Rte 606/Old Ox Rd, and will have to turn around at Mercure Circle to make the right into the jobsite.
-------------------------------------------------------------------------------------------
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.