Sept. 15, 2017
Concrete Delivery Schedule for Sept. 18 - 22
![]() WHAT: Stone delivery (20 trucks) of ballast material at the layup yard.
WHEN: Monday - Friday between the hours of 7 a.m. to 5 p.m.
HOW: Trucks will travel from Chantilly, coming from Rte 50, North on Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
WHAT: Precast Panel delivery (15 trucks) in 45 minute increments for installation at building TBD.
WHEN: Monday - Friday between the hours of 7 a.m. to 3 p.m.
HOW: Trucks will travel from Winchester, VA, East on Rte 7, South on 28, and West along Rte 606/Old Ox Rd to the project site, making the U-turn at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHAT: Concrete delivery (15 trucks) for installation in the Maintenance of Way Track including a 47m pump truck.
WHEN: Tuesday and Wednesday between the hours of 4 a.m. to 10 a.m.
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
WHAT: Concrete delivery (5 trucks) for installation in the TCR/TWF Footing.
WHEN: Wednesday, Thursday and Friday between the hours of 7 a.m. to 10 a.m.
HOW: Trucks will travel from the Titan batch plan along Rte 606/Old Ox Rd to the project site.
-----------------------------------------------------------------------------------------
WHAT: Turntable delivery (1 truck) for installation in the Service and Inspection Building.
WHEN: Monday and Tuesday between the hours of 6 a.m. to 11 a.m.
HOW: Trucks will travel from Connecticut, East on Rte 7, South on 28, and West along Rte 606/Old Ox Rd to the project site, making the U-turn at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
WHEN: Wednesday between the hours of 7 a.m. to 1 p.m.
HOW: Trucks will travel from Allentown, PA, South on 15, East on 267, South on Rte 606/Old Ox Rd and will have to turn around at Mercure Circle to make the right into the jobsite.
-----------------------------------------------------------------------------------------
<><><><><>
|