Concrete, Steel Deliveries Along Old Ox Rd/Route 606 Jan.3 - Jan. 6

  
Dec. 30, 2016 
 
CONTACT: Marcia McAllister
           T: 703-572-0506
           C: 571-730-9117
 
 
Concrete and Steel Deliveries Scheduled Along Old Ox Rd/Route 606 for Jan. 3 - Jan. 6
 
The following construction deliveries are scheduled for Jan. 3-6, 2017 (Tuesday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project Rail Yard and Maintenance Facility along U.S. Route 606 (Old Ox Road) and Mercure Circle as detailed below: 
 
WHAT: Concrete delivery (5-6 trucks) for installation at the Service and Inspection Building Footings (approximately 50 cubic yards). 
WHEN: Tuesday through Friday from 9 a.m. to 11 a.m. 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. 
 
 
WHAT: Concrete delivery (30-35 trucks) for installation at the Service and Inspection Building Wheel Truing Pit Upper Slab (approximately 300 cubic yards). This will include a 47 Meter Pump Truck. 
WHEN: Thursday and Friday from 7 a.m. to 10 a.m. 
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the project site. 
 
 
WHAT: Structural Steel Delivery (7-8 Trucks) for installation in the Service and Inspection Building. 
WHEN: Tuesday between the hours of 6 a.m. - 9 a.m. 
HOW: Trucks will be coming from Tennessee, traveling North on Old Ox Rd/Rt. 606 from US 50.
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.