Skip to main content
Silver Line on Track

Gravel and Fill Material Deliveries Scheduled Along Old Ox Rd/Route 606 for Oct. 24 - 28

  
October 22, 2016 
 
CONTACT:  Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
 
Gravel and Fill Material Deliveries Scheduled along Old Ox Road/Route 606 for Oct. 24 - 28
 
The following construction deliveries are scheduled for Oct. 24 - 28 (Monday - Friday) in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along US Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHATImport gravel from off-site location. 25 +/- truckloads of gravel will be delivered to project site daily for the construction of the retaining wall. The material will be used for backfill material. 
 
WHEN: Between the hours of 7 a.m. to 4 p.m. 
 
HOW: Trucks will travel to and from the project site along Old Ox Road (Rt. 606). 
----------------------------------------
 
WHAT: Import fill material from off-site location (Elm Street Site, Vienna VA). 100 - 150
Truckloads of fill material will be delivered to project site. The imported fill
material will be used to replace Unsuitable Material that was found on the
project site. All Unsuitable Material will remain on MWAA property and
stockpiled.

WHEN: Between the hours of 7 a.m. to 4 p.m.

HOW: Trucks will travel from the Vienna Site via Rt. 267 to Old Ox Road (Rt. 606).
Return trip will be Old Ox Road (Rt. 606) to Rt. 267 to the Vienna Site. Roads
will be cleaned during import fill operations by a sweeper truck.
 
<><><><><> 
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2, Package B construction-related issues: 952-939-6690. For general project information: www.dullesmetro.com or 703-572-0506.