Important Lane and Ramp Closures for the Week of April 2 - April 8

March 31, 2017
 
 
CONTACT: Marcia McAllister
                    T: 703-572-0506
                    C: 571-730-9117
                    marcia.mcallister@dullesmetro.com
 
 
Important Lane and Ramp Closures for the
Week of April 2 - April 8
 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2. Lane, shoulder, road and ramp closures will occur along the Dulles Toll Road, Dulles International Airport Access Highway, Dulles Greenway and surrounding roads during the week of April 2 - April 8. In addition, closures will occur along the Phase 1 alignment.
On or about Saturday, April 8, and Sunday, April 9, between midnight and 5 a.m., several 20-minute stoppages will occur on the westbound Dulles International Airport Access Highway (DIAAH) near mile marker 1.7 (8/10 mile past the Centreville Road bridge).
Drivers are asked to use caution remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions.
See below for more detailed information.  All work is weather permitting. 
 
<><><> 
Dulles Toll Road East
 
When:   Monday, April 3 - Friday, April 7, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
              Saturday, April 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 3.3 (from 1/10 mile past the Route 28 overpass to 1/10 mile before the Monroe Street overpass)
Why:     Civil work
 
When:   Monday, April 3 - Friday, April 7, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
              Saturday, April 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.2 (from 1/10 mile before the Monroe/Van Buren Street overpass to the Reston Parkway overpass)
Why:     Civil work
 
Dulles Toll Road West
 
When:   Friday, April 7 - Saturday, April 8, 7 p.m. to 5 a.m.
What:    Two left lanes closed
Where:  From mile marker 2.7 to 1.4 (from 1/10 mile before the Centreville Road bridge to 2/10 mile before the Route 28 overpass). Single left lane closed from 7 p.m. to 10 p.m., transitioning to two left lanes closed from 10 p.m. to 5 a.m.
Why:     Overhead sign installation       
 
When:   Monday, April 3 - Friday, April 7, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
              Saturday, April 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe/Van Buren Street overpass)
Why:     Civil work
 
When:   Monday, April 3 - Friday, April 7, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
              Saturday, April 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 1.5 (from 1/10 mile past the Monroe/Van Buren Street overpass to 3/10 mile before the Route 28 overpass)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Monday, April 3 - Saturday, April 8, 10 p.m. to 5 a.m.
What:    Full closure begins at 10 p.m.; follow detour. Road reopens at 5 a.m.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Aerial guideway construction
 
When:   Monday, April 3 - Saturday, April 8, 7 p.m. to 5 a.m.
What:    Two left lanes closed
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Aerial guideway construction
 
When:   Monday, April 3 - Friday, April 7, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
              Saturday, April 8, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 3.0 (from Saarinen Circle to 4/10 mile past the Centreville Road bridge)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Monday, April 3 - Friday, April 7, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
              Saturday, April 8, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.0 to 5.7 (from 4/10 mile before the Monroe/Van Buren Street overpass to 5/10 mile past the Reston Parkway overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Wednesday, April 5 - Thursday, April 6, 11:45 a.m. to 3:30 p.m.
What:    Right shoulder closed
Where:  From mile marker 8.3 to 9.0 (from 6/10 mile past Hunter Mill Road Bridge to 3/10 mile before the Beulah Road overpass)
Why:     Repairs to crossover gate
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Friday, April 7 - Saturday, April 8, 7 p.m. to 5 a.m.
What:    Two left lanes closed, 20 minute stoppages will occur between midnight and 5 a.m.
Where:  From mile marker 2.7 to 1.4 (from 1/10 mile before the Centreville Road bridge to 2/10 mile before the Route 28 overpass). Single left lane closed from 7 p.m. to 10 p.m., transitioning to two left lanes closed from 10 p.m. to 5 a.m., with 20 minute stoppages occurring between midnight and 5 a.m.
Why:     Overhead sign installation
 
When:   Monday, April 3 - Friday, April 7, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
              Saturday, April 8, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.0 (from 5/10 mile before the Reston Parkway overpass to 4/10 mile past the Monroe/Van Buren Street overpass)
Why:     Civil work
 
When:   Monday, April 3 - Friday, April 7, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
              Saturday, April 8, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.0 (from 5/10 mile before the Reston Parkway overpass to 4/10 mile past the Monroe/Van Buren Street overpass)
Why:     Civil work
 
When:   Monday, April 3 - Friday, April 7, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
              Saturday, April 8, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.3 to 200 feet past the ramp to Copilot Way, including ramps in the vicinity (from 2/10 mile past the Rudder Road overpass to Saarinen Circle past Garage 1)
Why:    Construction entrance acceleration/deceleration lane
 
When:   Monday, April 3 - Saturday, April 8, 10 p.m. to 5 a.m.
What:    Full closure
Where:  From mile marker 0.3 to Saarinen Circle (from 2/10 mile past the Rudder Road overpass to Saarinen Circle near Garage 1), traffic will be diverted around work area.
Why:    Aerial guideway construction
 
When:   Wednesday, April 5 - Thursday, April 6, 9:00 a.m. to 11:45 a.m.
What:    Right shoulder closed
Where:  From mile marker 7.5 to 6.5 (from 2/10 mile before Hunter Mill Road Bridge to 3/10 mile past Wiehle Avenue overpass)
Why:     Repairs to crossover gate
 
Copilot Way
 
When:   Monday, April 3 - Friday, April 7, 7 p.m. to 3 a.m.
What:    Full closure
Where:  From Saarinen Circle to the Garage 1 bus lane (buses will have full access to Garage 1 and the west end of Copilot Way).
Why:     Aerial guideway construction
 
Rudder Road West
 
When:   Monday, April 3 - Thursday, April 6, 6 p.m. to 5 a.m.
              Friday, April 7, 6 p.m. to Saturday, April 8, 10 p.m.
What:    Right lane closed
Where:  From the ramp to the Green Lot to the Blue Lot access road
Why:     Duct bank work
 
Dulles Greenway East
 
When:   Monday, April 3 - Friday, April 6, 10 a.m. to 6 pm.
              Saturday, April 7, 6 a.m. to 6 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 14.0 (from Broadlands Boulevard to the end of the ramp to the eastbound Dulles Toll Road), short lane closures of varying lengths will occur
Why:     Road work
 
When:   Monday, April 3 - Saturday, April 8, 8 p.m. to 5 a.m.
What:    Two right lanes closed OR two left lanes closed
Where:  From mile marker 11.0 to 12.0 (from the Old Ox Road overpass to 4/10 mile before the mainline toll plaza)
Why:     Aerial guideway construction
 
Dulles Greenway West
 
When:   Monday, April 3 - Friday, April 7, 6 a.m. to 3 p.m. and 8 p.m. to 6 a.m.
              Saturday, April 8, 6 a.m. to midnight
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile past the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
Sunrise Valley Drive West
 
When:   Monday, April 3 - Thursday, April 6, 9:30 a.m. to 3 p.m.
              Friday, April 7, 9:30 a.m. to noon
What:    Right lane closed
Where:  From Thunder Chase Drive to 200 feet past Hitchcock Drive
Why:     Clearing/excavation
 
Route 7 West
 
When:   Monday, April 3 - Thursday, April 6, 9:30 a.m. to 3:30 p.m.
What:    Left lane closed
Where:  From Route 123 north ramp to 1,000 feet passed Route 123 exit ramp
Why:     Curb realignment
 
When:   Sunday, April 2, 9:30 p.m. to 1 a.m.
What:    Close left lane
Where:  From Westpark Road to Spring Hill Road
Why:     Flushing, videotaping of storm drains
 
When:   Monday, April 3, 1 a.m. to 5 a.m.
What:    Close left lane
Where:  From Tyco Road to Industrial Way
Why:     Flushing, videotaping of storm drains
 
When:   Monday, April 3, 9:30 p.m. to 5 a.m.
What:    Close two right lanes
Where:  From Westpark Road to Spring Hill Road
Why:     Flushing, videotaping of storm drains
 
When:   Tuesday, April 4, 9:30 p.m. to 1 a.m.
What:    Close two right lanes
Where:  From Frontage to Spring Hill Road
Why:     Flushing, videotaping of storm drains
 
When:   Wednesday, April 5, 1 a.m. to 5 a.m.
What:    Close two right lanes
Where:  From Tyco Road to Industrial Way
Why:     Flushing, videotaping of storm drains
 
Route 7 East
 
When:   Monday, April 3 - Thursday, April 6, 9:30 a.m. to 3:30 p.m.
              Friday, April 7, 9:30 a.m. to 12:00 p.m.
What:    Left lane closed
Where:  From Gosnell Road to Marshalls Road
Why:     Curb realignment
 
Old Meadow Road Southbound
When:   Monday, April 3, to Thursday, April 6, 9:30 a.m. to 3:30 p.m.
What:    Close right lane
Where:  From Route 123 to 1,000 feet passed Route 123
Why:     Test pits for utility locations
Route 123 North
When:   Sunday, April 2, 9:30 p.m. to 1 a.m.
What:    Close right lane
Where:  From Old Meadow Road to Scotts Crossing Road
Why:     Flushing, videotaping of storm drains
 
Route 123 South
When:   Thursday, April 6, 9:30 p.m. to 5 a.m.
What:    Mobile operation in right lane
Where:  From north side of Scotts Crossing Road to International Drive
Why:     Flushing, videotaping of storm drains
 
Gosnell Road/Westpark Drive North
When:   Tuesday, April 4, 9:30 p.m. to 1 a.m.
What:    Close right lane
Where:  From south side of Route 7 to 500 feet north of Route 7
Why:     Flushing, videotaping of storm drains
 
Capital One Drive West
When:   Thursday, April 6, 1 a.m. to 5 a.m.
What:    Close right lane
Where:  From Route 7 to 600 feet west of Route 7
Why:     Flushing, videotaping of storm drains
 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.