Important Lane and Ramp Closures for the
Week of April 24 - April 30 (Version 2)
 
Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2.  Lane and shoulder closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Rudder Road, Dulles Greenway, Route 28, Centreville Road, Sunrise Valley Drive and Sunset Hills Road during the week of April 24 - April 30.
 
On or about Friday, April 29, at 10 p.m. to Monday, May 2, at 5 a.m., installation of a Tower Crane at the future Reston Station site will require the closure of the eastbound Dulles International Airport Access Highway (DIAAH) between the Fairfax County Parkway and Reston Parkway as follows:
 
Just prior to the Fairfax County Parkway, eastbound Dulles International Airport Access Highway (DIAAH) traffic will be diverted to a dedicated left lane on the eastbound Dulles Toll Road (DTR). Approximately 1 mile after entering the Dulles Toll Road (DTR), drivers will then be redirected back onto the eastbound Dulles International Airport Access Highway (DIAAH) near the Reston Parkway overpass. Drivers using this detour will NOT BE REQUIRED TO PAY A TOLL. Drivers are asked to use caution and remain attentive to all signage, barricades and adjusted speed limits. Large, slow-moving vehicles may be exiting and entering the highway at various times.
 
All work is weather permitting.
 
See below for more detailed information. 
 
<><><> 
 
Dulles Toll Road (DTR) East
 
When:   Sunday, April 24 - Saturday, April 30, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 3.3 (from 1/10 mile past the Route 28 overpass to 1/10 mile before the Monroe Street overpass)
Why:     Jack and bore, duct bank work
 
When:   Sunday, April 24 - Saturday, April 30, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.2 (from 1/10 mile before the Monroe Street overpass to the Reston Parkway overpass)
Why:     Jack and bore operations
 
When:   Friday, April 29, 10 p.m. - Monday, May 2, 5 a.m.
What:    Two left lanes closed
Where:  From mile marker 3.2 to 5.0 (from 2/10 mile before the Monroe Street overpass to 2/10 mile before the Reston Parkway overpass)
Why:     Tower crane installation
 
Dulles Toll Road (DTR) West
 
When:   Sunday, April 24 - Saturday, April 30, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, April 30 - Sunday, April 31, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.7 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass)
Why:     Jack and bore operations
 
When:   Sunday, April 24 - Saturday, April 29, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, April 30 - Sunday, April 31, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Left lane closed
Where:  From mile marker 3.5 to 1.5 (from 1/10 mile before the Monroe Street overpass to 3/10 mile before the Route 28 overpass)
Why:     Jack and bore operations
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Sunday, April 24 - Saturday, April 30, 9 p.m. to 5 a.m.
What:    Eastbound lane reductions begin at 9 p.m.  Eastbound full lane closures begin at 10 p.m.  Road reopens at 5 a.m. Follow detour.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Installation of a concrete span across the eastbound DIAAH. 
 
When:   Sunday, April 24 - Saturday, April 30, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., and Saturday, April 30 - Sunday, April 31, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 2.3 (from Saarinen Circle to 2/10 mile before the Centreville Road overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Sunday, April 24 - Saturday, April 30, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., and Saturday, April 30 - Sunday, April 31, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.4 (from 1/10 mile before the Monroe Street overpass to 2/10 mile past the Reston Parkway overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Friday, April 29, 10 p.m. - Monday, May 2, 5 a.m.
What:    Full closure of both eastbound DIAAH lanes
Where:  From mile marker 3.2 to 5.0 (from 2/10 mile before the Monroe Street overpass to 2/10 mile before the Reston Parkway overpass), all eastbound DIAAH traffic will be diverted to the left lane of the eastbound DTR (see details above in red).
Why:     Tower crane installation
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Sunday, April 24 - Monday, April 25, midnight to 2 p.m.
What:   Right lane closed
Where:  From mile marker 0.3 to 200 feet past the ramp to Copilot Way
Why:    Concrete pour
 
When:   Sunday, April 24 - Saturday, April 30, 8 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.3 to 200 feet past the ramp to Copilot Way, including ramps in the vicinity (from 2/10 mile past the Rudder Road overpass to Saarinen Circle past Garage 1)
Why:    Road work
 
When:   Sunday, April 24  - Saturday, April 30, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, April 30 - Sunday, April 31, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 0.6 (from 1/10 mile after the Monroe Street overpass to 1/10 mile before the Rudder Road overpass)
Why:    Duct bank work
 
When:   Sunday, April 24 - Saturday, April 30, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, April 30 - Sunday, April 31, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass)
Why:     Road work
 
Rudder Road West
 
When:   Sunday, April 24 - Saturday, April 30, 9 a.m. to 2 p.m.
What:    Right lane closed
Where:  From the ramp from the westbound DIAAH to Ariane Way/Blue Lot access road
Why:     Duct bank work
 
Dulles Greenway East
 
When:   Monday, April 25 - Friday, April 29, 10 a.m. to 5 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why:     Road work
 
Dulles Greenway West
 
When:   Monday, April 25 - Friday, April 29, 6 a.m. to 3 p.m.
 What:   Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
Route 28 South
 
When:   Monday, April 25 - Thursday, April 28, 9:30 a.m. to 3:30 p.m., and Friday, April 29, 9:30 a.m. to 12 p.m.
What:    Right lane closed
Where:  From the Dulles Toll Road overpass to the ramp to Frying Pan Road.
Why:     Electrical duct bank work
 
Centreville Road North and South
 
When:   Monday, April 25 - Friday, April 29, 10 p.m. to 5 a.m., and            Friday, April 29 - Saturday, April 30, 10 p.m. to 7 a.m.
What:    Right lane closed
Where:  Northbound and southbound Centreville Road between Woodland Park and Parcher Avenue.  Note:  Drivers may experience delays.
Why:     Overhead steel work at the Centreville Road Bridge
 
Sunset Hills Road East
 
When:   Monday, April 25 - Thursday, April 28, 9:30 a.m. to 3:30 p.m., and Friday, April 29, 9:30 a.m. to 12 p.m.
What:    Right lane closed
Where:  Between the Fairfax County Parkway and Reston Parkway
Why:     Excavation
 
Sunrise Valley Drive West
 
When:   Monday, April 25 - Friday, April 29, 8:30 a.m. to 3:30 p.m.
What:    Right lane closed
Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to 550 feet past Dulles Station Boulevard
Why:     Construction Deliveries
 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.