Important Lane and Ramp Closures for the Week of August 16 - August 22
Phase 2 Barrier Installation, Utility Work, and Other Construction Activities Continue along the Dulles Toll Road, Dulles International Airport Access Highway, Dulles Greenway and Airport Roads
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, barrier installation, utility work, and other construction activities. Lane and shoulder closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway and Autopilot Drive the week of August 16 – August 22.
<><><>
Dulles Toll Road (DTR) East
When: Sunday, August 16 - Saturday, August 22, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 0.6 to 5.7 (from the overpass of the ramp to the northbound Dulles
Greenway to 5/10 mile after the Reston Parkway overpass)
Why: Jack and bore operations
When: Sunday, August 16 - Saturday, August 22, 10 a.m. to 3 p.m.
What: Ramp narrows, left and right side
Where: Along the ramp to the eastbound DTR from southbound Route 28, and along the ramp from the eastbound DTR to northbound Route 28
Why: Jack and bore operations
Dulles Toll Road (DTR) West
When: Sunday, August 16 - Saturday, August 22, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 5.7 to 0.6 (from 5/10 mile before the Reston Parkway overpass to the overpass of the ramp to the northbound Dulles Greenway)
Why: Jack and bore operations
Dulles International Airport Access Highway (DIAAH) East
When: Sunday, August 16, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
Monday, August 17 - Friday, August 21, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
Saturday, August 22, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 3.2 to 5.7 (from 2/10 mile before the Monroe Street overpass to 5/10 mile after the Reston Parkway overpass)
Why: Construction entrance acceleration/deceleration lane
When: Sunday, August 16, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
Monday, August 17 - Friday, August 21, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
Saturday, August 22, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 0.3 to 2.7 (from 2/10 mile before the Rudder Road overpass to 2/10 mile past the Centreville Road overpass)
Why: Construction entrance acceleration/deceleration lane
Dulles International Airport Access Highway (DIAAH) West
When: Sunday, August 16, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
Monday, August 17 - Friday, August 21, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
Saturday, August 22, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 2.7 to 0.3 (from 2/10 mile before the Centreville Road overpass to 2/10 mile past the Rudder Road overpass)
Why: Construction entrance acceleration/deceleration lane
When: Sunday, August 16, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
Monday, August 17 - Friday, August 21, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
Saturday, August 22, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: From mile marker 5.7 to 3.2 (from 5/10 mile before the Reston Parkway overpass to 2/10 mile after the Monroe Street overpass)
Why: Construction entrance acceleration/deceleration lane
When: Sunday, August 16, 8 a.m. to 2 p.m. and 10 p.m. to 5 a.m.
Monday, August 17 - Friday, August 21, 8 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
Saturday, August 22, 8 a.m. to 2 p.m. and 10 p.m. to 8 a.m.
What: Alternating right and left lane closures
Where: From mile marker 0.3 to 200 feet past Copilot Way (from 2/10 mile after the Rudder Road overpass, continuing along Saarinen Circle past Daily Garage 1), including ramps in the vicinity of Daily Garage 1
Why: Road widening
Dulles Greenway East
When: Monday, August 17 - Friday, August 21, 10 a.m. to 5 a.m.
What: Right lane closed
Where: From mile marker 14.0 where the overpass crosses Route 28 to the intersection of the
eastbound Dulles Greenway and the eastbound DTR
Why: Barrier installation
When: Monday, August 17 - Friday, August 21, 10 a.m. to 5 p.m.
What: Alternating right and left lane closures of varying lengths
Where: Between mile marker 8.6 and 12.2 (from 1/10 mile after the Ashburn Village Boulevard
overpass to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why: Road work
Dulles Greenway West
When: Monday, August 17 through Friday, August 21, 8 p.m. to 5 a.m.
What: Alternating right and left lane closures of varying lengths
Where: Between mile marker 12.0 and 8.6 (from 3/10 mile after the mainline toll plaza to 1/10 mile before the Ashburn Village Boulevard overpass), short lane closures of varying lengths will occur
Why: Road work
Autopilot Drive
When: Sunday, August 16 - Saturday, August 22, 9 p.m. to 5 a.m.
What: Full closure of northbound lanes
Where: Northbound lanes of Autopilot Drive from Rudder Road to Materials Road closed;
northbound traffic will be shifted to the southbound lanes
Why: Superstructures work
When: Sunday, August 16 - Saturday, August 22, 9 p.m. to 5 a.m.
What: Alternating right and left lane closures
Where: Northbound Autopilot Drive from Rudder Road to the Avis entrance
Why: Utility work
<><><><><>
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.