Dulles Toll Road (DTR) East
 
When:   Sunday, Feb. 28 and Monday, Feb. 29, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What:    Alternating right and left lane closures of varying length
Where:  From mile marker 4.5 to 5.7 (between the Reston Parkway and Wiehle Avenue overpasses)
Why:     Jack and bore operations
 
When:   Sunday, Feb. 28 and Monday, Feb. 29 - 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What:    Left lane closed
Where:  From mile marker 2.5 to 4.5 (between the Centreville Road and Reston Parkway overpasses)
Why:     Jack and bore operations
 
Dulles Toll Road (DTR) West
 
When:   Wednesday, March 2 - Saturday, March 5, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.7 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass)
Why:     Jack and bore operations
 
When:   Wednesday, March 2 - Saturday, March 5, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, March 5, 10 a.m. to 3:30 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.5 to 1.5 (between the Fairfax County Parkway overpass and Route 28)
Why:     Jack and bore operations
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Sunday, Feb. 28 - Saturday, March 5, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., and Saturday, March 5, 5 a.m. to 2 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.5 to 3.5 (Route 28 and the Fairfax County Parkway)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Monday, Feb. 29 - Saturday, March 5, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.7 to 5.7 (from Monroe Street overpass to the Reston Parkway overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Sunday, Feb. 28 - Saturday, March 5, 9 p.m. to 5 a.m. 
What:    Eastbound lane reductions begin at 9 p.m.  Eastbound full lane closures begin at 10 p.m.  Road reopens at 5 a.m. Follow detour.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Installation of a concrete span across the eastbound DIAAH. 
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Sunday, Feb. 28 - Friday, March 4, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, March 5, 5 a.m. to 2 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.5 to 1.5 (between the Fairfax County Parkway overpass and Route 28)
Why:    Construction entrance acceleration/deceleration lane
 
When:   Sunday, Feb. 28 - Friday, March 4, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, March 5, 5 a.m. to 2 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.7 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass)
Why:     Construction entrance acceleration/deceleration lane
 
Dulles Greenway East
 
When:   Monday, Feb. 29 - Thursday, March 4, 10 a.m. to 5 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why:     Road work
 
When:   Saturday, Feb. 27, 10 a.m. to 5 p.m.
What:    Left shoulder closure
Where:  Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza)
Why:     Road work
 
Dulles Greenway West
 
When:   Monday, Feb. 29 - Friday, March 4, 6 a.m. to 3 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.0 and 7.6 (from 3/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
When:   Saturday, Feb. 27, 6 a.m. to 5 p.m.
What:    Left lane
Where:  Between mile marker 12.0 and 7.6 (from 2/10 mile before the mainline toll plaza to Broadlands Boulevard)
Why:     Road work
 
Autopilot Drive
 
When:   Monday, Feb. 29 - Wednesday, March 2, 5, 9 a.m. to 2 p.m.
What:    Left lane closed
Where:  Westbound Aviation Drive at the intersection of Autopilot Drive
Why:     Fiber line
 
When:   Sunday, Feb. 28 - Saturday, March 5, 9 p.m. to 5 a.m.
What:    Northbound lanes closed; northbound traffic diverted to one southbound lane.
Where:  Autopilot Drive from Rudder Road to Materials Road
Why:     Superstructures work
 
Sunset Hills Road East
 
When:   Sunday, Feb. 28 - Tuesday, March 1, 9:30 a.m. to 3:30 p.m.
What:    Right lane closed
Where:  Between Fairfax County Parkway and Reston Parkway
Why:     Excavation
 
Sunrise Valley Drive West
 
When:   Monday, Feb. 29 - Thursday, March 3, 8:30 a.m. to 3:30 p.m., and Friday, March 4, 8:30 a.m. to 12 p.m.
What:    Right lane closed
Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to 550 feet past Dulles Station Boulevard
Why:     Construction Deliveries
 

Old Ox Road (Route 606)
 
When:   Monday, Feb. 29 - Friday, March 4, 1:45 p.m. to 2:30 p.m.
What:    Five-minute road closures in both directions
Where:  From Commerce Center Court to Mercure Circle
Why:     Rock blasting
 
<><><><><>
 