Important Lane and Ramp Closures for the Week of July 17 - July 23

 
July 15, 2016                                                 
 
 
CONTACT: Marcia McAllister
                   T: 703-572-0506
                   C: 571-730-9117
                   marcia.mcallister@dullesmetro.com
 
 
Important Lane and Ramp Closures for the
Week of July 17 - July 23
 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2. Lane and shoulder closures will occur along the Dulles Toll Road, Dulles International Airport Access Highway, Rudder Road, Dulles Greenway, Sunrise Valley Drive and Sunset Hills Road during the week of July 17 - July 23.
 
All work is weather permitting.
 
See below for more detailed information. 
 
<><><> 
 

Dulles Toll Road East

 

When:   Sunday, July 17 - Saturday, July 23, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 1.3 to 3.3 (from 1/10 mile past the Route 28 overpass to 1/10 mile before the Monroe Street overpass)

Why:     Jack and bore, duct bank work

 

When:   Sunday, July 17 - Saturday, July 23, 9 p.m. to 3:30 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 3.3 to 5.2 (from 1/10 mile before the Monroe Street overpass to the Reston Parkway overpass)

Why:     Jack and bore operations

 

Dulles Toll Road West

 

When:   Sunday, July 17, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m., Monday, July 18 - Friday, July 22,  9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, July 23, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass)

Why:     Jack and bore operations

 

When:   Monday, July 18 - Wednesday, July 20,  10 p.m. to 4 a.m.

What:    Two left lanes closed

Where:  From mile marker 2.5 to 1.5 (from the Centreville Road bridge to 3/10 mile before the Route 28 overpass)

Why:     Duct bank work

 

When:   Sunday, July 17, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m., Monday, July 18 - Friday, July 22,  9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, July 23, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.

What:    Left lane closed

Where:  From mile marker 3.5 to 1.5 (from 1/10 mile before the Monroe Street overpass to 3/10 mile before the Route 28 overpass)

Why:     Jack and bore operations

 

Dulles International Airport Access Highway (DIAAH) East

 

When:   Sunday, July 17 - Saturday, July 23, 9 p.m. to 5 a.m.

What:    Eastbound lane reductions begin at 9 p.m.  Eastbound full closure begins at 10 p.m.  Road reopens at 5 a.m. Follow detour.

Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)

Why:     Installation of a concrete span across the eastbound DIAAH.

 

When:   Sunday, July 17, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m., Monday, July 18 - Friday, July 22, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m., and Saturday, July 23, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 0.0 to 2.3 (from Saarinen Circle to 2/10 mile before the Centreville Road overpass)

Why:     Construction entrance acceleration/deceleration lane

 

When:   Sunday, July 17, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m., Monday, July 18 - Friday, July 22, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m., and Saturday, July 23, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 3.3 to 5.4 (from 1/10 mile before the Monroe Street overpass to 2/10 mile past the Reston Parkway overpass)

Why:     Construction entrance acceleration/deceleration lane

 

Dulles International Airport Access Highway (DIAAH) West

 

When:   Sunday, July 17, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Monday, July 18 - Friday, July 22,  7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, July 23, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 3.3 to 0.3 (from 1/10 mile past the Monroe Street overpass to 2/10 mile past the Rudder Road overpass)

Why:    Duct bank work

 

When:   Sunday, July 17, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Monday, July 18 - Friday, July 22,  7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, July 23, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass)

Why:     Road work

 

When:   Sunday, July 17, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Monday, July 18 - Friday, July 22,  7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, July 23, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 0.3 to 200 feet past the ramp to Copilot Way, including ramps in the vicinity (from 2/10 mile past the Rudder Road overpass to Saarinen Circle past Garage 1)

Why:    Construction entrance acceleration/deceleration lane

 

Rudder Road West

 

When:   Sunday, July 17, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m., Monday, July 18 - Friday, July 22,  9 a.m. to 2 p.m. and 6 p.m. to 5 a.m., and Saturday, July 16, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.

What:    Right lane closed

Where:  From the ramp from the westbound DIAAH to Ariane Way/Blue Lot access road

Why:     Duct bank work

 

Dulles Greenway East

 

When:   Monday, July 18 - Friday, July 22, 10 a.m. to 7 p.m. and 7 p.m. to 5 a.m. and Saturday, July 23, 5 a.m. to midnight

What:    Alternating right and left lane closures of varying lengths

Where:  Between mile marker 7.6 and 14.0 (from Broadlands Boulevard to the end of the ramp to the eastbound Dulles Toll Road), short lane closures of varying lengths will occur

Why:     Road work

 

Dulles Greenway West

 

When:   Monday, July 18 - Friday, July 22, 6 a.m. to 3 p.m. and 8 p.m. to 6 a.m. and Saturday, July 23, 6 a.m. to midnight

 What:   Alternating right and left lane closures of varying lengths

Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur

Why:     Road work

 

Sunset Hills Road East

 

When:   Monday, July 18 - Thursday, July 21, 9:30 a.m. to 3:30 p.m. and Friday, July 22, 9:30 a.m. to noon

What:    Right lane closed

Where:  Between the Fairfax County Parkway and Reston Parkway

Why:     Excavation

 

Sunrise Valley Drive East

 

When:   Monday, July 18 - Saturday, July 23, 8:30 a.m. to 3:30 p.m.

What:    Right shoulder closed and right lane narrows

Where:  Eastbound Sunrise Valley Drive from 700 feet west of Dulles Station Boulevard to just before Dulles Station Boulevard. 

Why:     Water line installation

 

Sunrise Valley Drive West

 

When:   Monday, July 18 - Saturday, July 23, 8:30 a.m. to 3:30 p.m.

What:    Right lane closed

Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to 550 feet past Dulles Station Boulevard

Why:     Construction Deliveries

 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.