Skip to main content
Silver Line on Track

Important Lane and Ramp Closures for the Week of July 5 - July 9

 
July 1, 2016                                                 
 
 
CONTACT: Marcia McAllister
                     T: 703-572-0506
                     C: 571-730-9117
                     marcia.mcallister@dullesmetro.com
 
 
Important Lane and Ramp Closures for the
Week of July 5 - July 9
 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2. Lane and shoulder closures will occur along the Dulles Toll Road, Dulles International Airport Access Highway, Rudder Road, Dulles Greenway, Sunrise Valley Drive and Sunset Hills Road during the week of July 5 - July 9.
 
All work is weather permitting.
 
See below for more detailed information. 
 
<><><> 
 
Dulles Toll Road East
 
When  Tuesday, July 5, noon to 3:30 p.m. and 8 p.m. to 5 a.m., Wednesday, July 6 - Saturday, July 9,  10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 3.3 (from 1/10 mile past the Route 28 overpass to 1/10 mile before the Monroe Street overpass)
Why:  Jack and bore, duct bank work
 
When:  Tuesday, July 5, noon to 3:30 p.m. and 8 p.m. to 5 a.m., Wednesday, July 6 - Saturday, July 9,  10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.2 (from 1/10 mile before the Monroe Street overpass to the Reston Parkway overpass)
Why:  Jack and bore operations
 
Dulles Toll Road West
 
When:  Tuesday, July 5, noon to 3 p.m. and 8 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., Saturday, July 9, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass)
Why:  Jack and bore operations
 
When:  Tuesday, July 5, noon to 3 p.m. and 8 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., Saturday, July 9, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:  Left lane closed
Where:  From mile marker 3.5 to 1.5 (from 1/10 mile before the Monroe Street overpass to 3/10 mile before the Route 28 overpass)
Why:  Jack and bore operations
 
Dulles International Airport Access Highway (DIAAH) East
 
When:  Tuesday, July 5 - Saturday, July 9, 9 p.m. to 5 a.m.
What:  Eastbound lane reductions begin at 9 p.m.  Eastbound full closure begins at 10 p.m.  Road reopens at 5 a.m. Follow detour.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:  Installation of a concrete span across the eastbound DIAAH.
 
When:  Tuesday, July 5, noon to 3 p.m. and 6 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8,  8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m., Saturday, July 9, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 2.3 (from Saarinen Circle to 2/10 mile before the Centreville Road overpass)
Why:  Construction entrance acceleration/deceleration lane
 
When:  Tuesday, July 5, noon to 3 p.m. and 6 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8,  8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m., Saturday, July 9, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.4 (from 1/10 mile before the Monroe Street overpass to 2/10 mile past the Reston Parkway overpass)
Why:  Construction entrance acceleration/deceleration lane
 
Dulles International Airport Access Highway (DIAAH) West
 
When:  Tuesday, July 5, noon to 2 p.m. and 7 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8,  7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Saturday, July 9, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 0.3 (from 1/10 mile past the Monroe Street overpass to 2/10 mile past the Rudder Road overpass)
Why:  Duct bank work
 
When:  Tuesday, July 5, noon to 2 p.m. and 7 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8,  7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Saturday, July 9, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass)
Why:  Road work
 
When:  Tuesday, July 5, noon to 2 p.m. and 7 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8,  7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Saturday, July 9, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:  Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.3 to 200 feet past the ramp to Copilot Way, including ramps in the vicinity (from 2/10 mile past the Rudder Road overpass to Saarinen Circle past Garage 1)
Why:  Construction entrance acceleration/deceleration lane
 
When:  Tuesday, July 5 - Saturday, July 9, 9 p.m. to 5 a.m.
What:  Full closure of westbound DIAAH
Where:  From mile marker 0.3 to Saarinen Circle (from 2/10 mile past the Rudder Road overpass to Saarinen Circle near Garage 1), traffic will be diverted around work area
Why:  Installation of a concrete span across the westbound DIAAH. 
 
Rudder Road West
 
When:  Tuesday, July 5, noon to 2 p.m. and 6 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8,  9 a.m. to 2 p.m. and 6 p.m. to 5 a.m., Saturday, July 9, 5 a.m. to 2 p.m.
What:  Right lane closed
Where:  From the ramp from the westbound DIAAH to Ariane Way/Blue Lot access road
Why:  Duct bank work
 
Dulles Greenway East
 
When:  Tuesday, July 5, noon to 6 p.m. and 6 p.m. to 5 a.m., Wednesday, July 6 - Friday, July 8,  10 a.m. to 6 p.m. and 6 p.m. to 5 a.m., Saturday, July 9, 5 a.m. to midnight
What:  Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 14.0 (from Broadlands Boulevard to the end of the ramp to the eastbound Dulles Toll Road), short lane closures of varying lengths will occur
Why:  Road work
 
Dulles Greenway West
 
When:  Tuesday, July 5, noon to 3 p.m. and 8 p.m. to 6 a.m., Wednesday, July 6 - Friday, July 8,  6 a.m. to 3 p.m. and 8 p.m. to 6 a.m., Saturday, July 9, 6 a.m. to midnight
What:  Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:  Road work
 
Sunset Hills Road East
 
When:  Tuesday, July 5, noon to 3:30 p.m., Wednesday, July 6 and Thursday, July 7, 9:30 a.m. to 3:30 p.m., Friday, July 8, 9:30 a.m. to noon
What:  Right lane closed
Where:  Between the Fairfax County Parkway and Reston Parkway
Why:  Excavation
 
Sunrise Valley Drive West
 
When:  Tuesday, July 5, noon to 3:30 p.m., Wednesday, July 6 - Friday, July 8, 8:30 a.m. to 3:30 p.m.
What:  Right lane closed
Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to 550 feet past Dulles Station Boulevard
Why:  Construction Deliveries
 
Sunrise Valley Drive East
 
When:  Tuesday, July 5, noon to 3:30 p.m., Wednesday, July 6 - Friday, July 8, 8:30 a.m. to 3:30 p.m.
What:  Right shoulder and right lane closed
Where:  Eastbound Sunrise Valley Drive from 700 feet west of Dulles Station Boulevard to just before Dulles Station Boulevard. 
Why:  Water line installation
 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.