Important Lane and Ramp Closures for the Week of June 3 - 9

 
June 1, 2018
                                                                      
 
CONTACT: Marcia McAllister
                    T: 703-572-0506
                    C: 571-730-9117
                    marcia.mcallister@dullesmetro.com
 
 
Important Lane and Ramp Closures for the
Week of June 3 - 9
 
Dulles Corridor Metrorail Project crews continue construction activities for the Metrorail Silver Line, Phase 2, that require lane, shoulder, and road closures, and paving detours at locations along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Reston Parkway, Herndon Parkway, Sunrise Valley Drive, and Sunset Hills Road during the week of June 3 - 9. In addition, lane closures are planned along Route 7 and Route 123 to permit work on bus bays near the Spring Hill and McLean stations.
 
SPECIAL NOTICE: Dulles Toll Road West
Overhead utility work under the Innovation Station South Pedestrian Bridge will require a closure of the westbound DTR. DTR traffic will be diverted onto the Centreville Road Exit. Signs will direct traffic to turn left onto Centreville Road, right onto Frying Pan Road, and take the Route 28 north exit toward Dulles Airport and all points north; or the Route 28 south exit toward Centreville and all points south.
 
SPECIAL NOTICE: Dulles Access Highway and Dulles Toll Road East: Construction activities at the Innovation, Herndon and Reston Metrorail Stations will continue to require nighttime closures on the eastbound Dulles Access Highway. During the closures, traffic will be detoured onto the eastbound Dulles Toll Road then returned to the Access Highway after the construction zone.
 
See below for more specific dates, times and details and remember that all work is weather permitting.
 
PLEASE USE CAUTION and remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions. Slow-moving vehicles and equipment may be entering and exiting the highways and surrounding roads.
 
<><><> 
 
Dulles Toll Road East and Dulles Access Highway East
 
When:   Monday, June 4 and Tuesday, June 5, 9:30 p.m. to 5 a.m.
What:    Full closure of a section of the eastbound DIAAH
Where:  From mile marker 0.8 to 5.1 (between 3/10 mile east of the Rudder Road overpass
between the Centreville Road and Fairfax County Parkway overpasses) 
Detour: Eastbound DIAAH traffic will be diverted onto the left lane of the eastbound Dulles Toll Road and then returned to the eastbound DIAAH beyond the construction activity. The left lane of the Dulles Toll Road Route 28 Toll Booth will be closed.
Why:     Construction activities at Innovation, Herndon, and Reston Stations
 
When:   Friday, June 1 - Sunday, June 3, 9:30 p.m. to 5 a.m. and
             Friday, June 8 - Sunday, June 10, 9:30 p.m. to 5 a.m.
What:    Full closure of a section of the eastbound DIAAH
Where: 
From mile marker 0.8 to 5.1 (between 3/10 mile east of the Rudder Road overpass between the Centreville Road and Fairfax County Parkway overpasses) 
Detour: Eastbound DIAAH traffic will be diverted onto the left lane of the eastbound Dulles Toll Road and then returned to the eastbound DIAAH beyond the construction activity
Why:     Weather back-up dates for construction activities at Innovation, Herndon and Reston Stations
 
Dulles Toll Road East
 
When:   Monday, June 4 - Friday, June 8, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
             Saturday, June 9, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 5.7 (from just west of the Route 28 overpass to the Reston Parkway overpass)
Why:     Civil work
 
Dulles Toll Road West
 
When:   Monday, June 4 - Friday, June 8, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
             Saturday, June 9, 10 a.m. to 3:30 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 1.5 (from approximately 2/10 mile after the Wiehle Avenue overpass to 3/10 mile before the Route 28 overpass)
Why:     Civil work
 
When:   Friday, June 8 - Saturday, June 9, 10 p.m. to 6 a.m.
What:    Full closure of portion of westbound Dulles Toll Road
Where:  From mile marker 4.6 to 1.8 (from 6/10 mile west of Reston Parkway to approximately 8/10 mile west of Centreville Road overpass) Detour: At mile marker 2.7, westbound DTR traffic will be diverted onto the Centreville Road Exit. Signs will direct traffic to turn left onto Centreville Road, right onto Frying Pan Road, and take the Route 28 north exit toward Dulles Airport and all points north; or the Route 28 south exit toward Centreville and all points south
Why:     Overhead utility work on the Innovation Station North Pedestrian Bridge
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Monday, June 4 - Friday, June 8, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m.
Saturday, June 9, 5 a.m. to 2 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 5.7 (from the Aviation Drive overpass to 5/10 mile after the Reston Parkway overpass)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Monday, June 4 - Friday, June 8, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m
Saturday, June 9, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 7.3 to 0.0 (from approximately 7/10 mile west of Hunter Mill Road to approximately 200 feet beyond the Copilot Way ramp on Saarinen Circle near the Dulles Airport Terminal)
Why:     Civil and Dulles Metrorail Station work will be taking place within the closures
 
Dulles Greenway East
 
When:   Monday, June 5 - Friday, June 8, 10 a.m. to 6 p.m. and 6 p.m. to 5 a.m.
             Saturday, June 9, 6 a.m. to 6 p.m.
What:    Alternating left and right lane closures of varying lengths
Where:  Lane closures between mile markers 7.6 and 14.0 (between Exit 5/Claiborne Parkway and Exit 7/Loudoun County Parkway)
Why:     Civil work
 
When:   Monday, June 4 - Thursday, June 7, 4 p.m. to 5 a.m.
What:    Alternating double left and right lane closures of varying lengths and intermittent 20 minute ramp stoppages
Where:  Lane closures between mile markers 8.7 and 10.6 (between the Ashburn Village Boulevard and Old Ox Road overpasses)
Why:     Paving
 
Dulles Greenway West
 
When:   Monday, June 4 - Friday, June 8, 6 a.m. to 3 p.m. and 8 p.m. to 6 a.m.
Saturday, June 9, 6 a.m. to 6 p.m.
What:    Alternating left and right lane closures of varying lengths
Where:  From mile marker 12.2 to 7.6 (begin approximately 3/10 mile west of the Main Toll Plaza and near the Broadlands Boulevard overpass)
Why:     Civil work
 
Sunset Hills Road East
 
When:   Monday, June 4 - Thursday, June 7, 9:30 a.m. to 3:30 p.m.
             Friday, June 8, 9:30 a.m. to noon
What:    Right lane closed
Where:  From 400 feet west of Town Center Parkway for approximately 3/10 of a mile
Why:     Civil work
 
Sunrise Valley Drive East and West
 
When:   Monday, June 4 - Thursday, June 7, 9:30 a.m. to 3:30 p.m.
             Friday, June 8, 9:30 a.m. to noon
What:    Right lane closed
Where:  From Thunderchase Road to 200 feet beyond Hitchcock Drive
Why:     Civil work
 
Sunrise Valley Drive East
 
When:   Monday, June 4 - Thursday, June 7, 9:30 a.m. to 3:30 p.m.
             Friday, June 8, 9:30 a.m. to noon
What:    Right lane closed
Where:  From Edmund Halley Drive to Reston Parkway
Why:     Civil work
 
Reston Parkway
 
When:   Monday, June 4, Noon to 3:30 p.m.
Wednesday, June 6 - Thursday, June 7, 9:30 a.m. to 3:30 p.m.
             Friday, June 8, 9:30 a.m. to noon
What:    Alternating closures of the right lanes of //north and south Reston Parkway
Where:  At the intersection of Sunrise Valley Drive and Reston Parkway
Why:     Civil work
 
Herndon Parkway East
 
When:   Monday, June 4 - Thursday, June 7, 9:30 a.m. to 3:30 p.m.
             Friday, June 8, 9:30 a.m. to noon
What:    Right lane closure
Where: From 1000 feet east of Van Buren Street to 800 feet west of Exchange Place
Why:     Civil work
 
Route 7 West
 
When:  Monday, June 4, through Thursday, June 7, from 9 a.m. to 3 p.m.
Friday, June 8, 9 a.m. to 1 p.m.
What:    Close right lane
Where:  From Schmitz Exxon entrance to the Bentley/Aston Martin dealers' entrance
Why:     Repairs of concrete panels, and curb and gutter, at Spring Hill Station bus bays
 
        * Drivers turning left from Westwood Center Drive or right from Spring Hill Road to Route 7 west toward Route 267 should note the closing of this section of Route 7.
 
Route 123 South
When:  Monday, June 4, through Thursday, June 7, 9:30 a.m. to 3 p.m.
             Friday, June 8, 9:30 a.m. to 1 p.m.
What:    Close right turn lane
Where:  From 500 feet after Scotts Crossing Road to Capital One Tower Drive
Why:     Repairs of concrete panels, and curb and gutter, at McLean Station bus bays
 
<><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.