Important Lane and Ramp Closures for the Week of June 3 - June 8
 
Dulles Corridor Metrorail Project crews continue construction activities for the Metrorail Silver Line Phase 2 that require lane, shoulder, and road closures and detours at locations along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Autopilot Drive, Herndon Parkway, Edmund Halley Drive, Sunrise Valley Drive, Sunset Hills Road, Lockridge Road, and Moran Road during the week of June 3 - June 8, 2019. In addition, there will be lane closures along the Phase 1 alignment as listed below.
 
See below for more specific dates, times and details and remember that all work is weather permitting.
 
PLEASE USE CAUTION and remain attentive to all signage, barricades and speed limits, and obey all police and flagger instructions. Slow-moving vehicles and equipment may be entering and exiting the highways and surrounding roads.
 
<><><> 
Dulles Toll Road East
When:   Monday, June 3 to Friday, June 7, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m., Saturday, June 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 5.2 (from just west of the Route 28 overpass to the Reston Parkway overpass)
Why:     Civil work
 
When:   Sunday, June 2 to Thursday, June 6, 10 p.m. to 4 a.m., and Friday, June 7 to Saturday, June 8, 11 p.m. to 5 a.m.
What:    Alternating double right and left lane closures of varying lengths
Where:  From mile marker 2.4 to 4.1 (from Centreville Road to Fairfax County Parkway)
Why:     Milling, Paving, Striping
 
When:   Sunday, June 2 to Saturday, June 7, 10 p.m. to 5 a.m.
What:    Alternating double right and left lane closures of varying lengths
Where:  From mile marker 2.2 to 4.2 (from Centreville Road to Fairfax County Parkway)
Why:     Milling, Paving, Striping
 
Dulles Toll Road West
When:   Monday, June 3 to Friday, June 7, 9 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, June 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 1.5 (between the Route 28 and Reston Parkway overpasses)
Why:     Civil work
 
Dulles International Airport Access Highway (DIAAH) East
When:   Monday, June 3 to Friday, June 7, 8:30 a.m. to 3 p.m. and 6 p.m. to 5 a.m., and Saturday, June 8 to Sunday June 2, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 8.0 (from the Aviation Drive overpass to Hunter Mill Road)
Why:     Civil work

When:   Monday, June 3 to Thursday, June 6, 10 p.m. to 5 a.m., and Friday, June 7 and Sunday June 9, 10 p.m. to 5 a.m.
What:    Detour
Where:  From mile marker 2.7 to 4.0 (from Centreville Road to just east of Herndon Station)
Why:     Civil work
 
When:   Sunday, June 2 to Saturday, June 8, 12 a.m. to 11:59 p.m.
What:    Left shoulder closure
Where:  From mile marker 3.5 to 5.5 (from Van Buren Street to 3/10 mile east of Reston Parkway)
Why:     Storm sewer flushing
 
When:   Sunday, June 2 to Saturday, June 7, 10 p.m. to 5 a.m.
What:    Detour
Where:  From mile marker 2.7 to 4.0 (Centreville Road Bridge to 2/10ths of a mile west of the Fairfax County Parkyway Overpass)
Why:     Milling/Paving 
 
Dulles International Airport Access Highway (DIAAH) West
When:   Monday, June 3 to Friday, June 7, 7:30 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, June 8 to Sunday June 9, 5 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 7.3 to 0.0 (from approximately 7/10 mile west of Hunter Mill Road to approximately 200 feet beyond the Copilot Way ramp on Saarinen Circle near the Dulles Airport Terminal)
Why:     Civil and Dulles Airport Metrorail Station work will be taking place within the closures 
 
When:   Monday, June 3 to Friday, June 7, 7:30 a.m. to 2 p.m. and 10 p.m. to 5 a.m., and Saturday, June 8 to Sunday June 9, 5 a.m. to 2 p.m. and 10 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.3 to approximately 200 feet beyond the Copilot Way ramp on Saarinen Circle near the Dulles Airport Terminal
Why:     Civil and Dulles Airport Metrorail Station work will be taking place within the closures
 
When:   Monday, June 3 to Friday, June 7, 10 p.m. to 5 a.m.
What:    Alternating double right and left lane closures of varying lengths
Where:  From mile marker 1.3 to approximately 300 feet beyond the Copilot Way ramp on Saarinen Circle near the Dulles Airport Terminal
Why:     Civil work, Paving, Dulles Station work
 
When:   Monday, June 3 to Thursday, June 6, 10 p.m. to 5 a.m., and Friday, June 7 and Sunday June 9, 10 p.m. to 5 a.m.
What:    Detour
Where:  From mile marker 9.1 to 3.0 (from Beluah Road to Centreville Road)
Why:     Milling, paving, striping
 
When:   Sunday, June 2 to Saturday, June 8, 12 a.m. to 11:59 p.m.
What:    Left shoulder closure
Where:  From mile marker 3.5 to 5.5 (from Van Buren Street to 3/10 mile east of Reston Parkway)
Why:     Storm sewer flushing
 
Dulles Connector Road - East
When:  Monday, June 3, through Friday, June 7, 11 a.m. - 3 p.m.

What:   Left lane closure
Where: From 500 feet before Margarity Road Overpass to 2500 feet after Margarity Road Overpass
Why:    Grading for drainage

Dulles Greenway East
When:   Monday, June 3 to Friday, June 7, 10 a.m. to 6 p.m. and 6 p.m. to 5 a.m., and Saturday, June 8, 6 a.m. to 6 p.m. and 6 p.m. to 5 a.m.
What:    Alternating left and right lane closures of varying lengths
Where:  From mile marker 7.6 to 14.0 (from approximately 2/10 mile west of Waxpool Road to the Dulles Toll Road)
Why:     Civil work

Dulles Greenway West
When:   Monday, June 3 to Friday, June 7, 6 a.m. to 3 p.m. and 8 p.m. to 6 a.m., and Saturday, June 8, 6 a.m. to 6 p.m. and 8 p.m. to 6 a.m.
What:    Alternating left and right lane closures of varying lengths
Where:  From mile marker 12.2 to 7.6 (from the Moran Road exit to Broadlands Boulevard overpass)
Why:     Civil work
 
Rudder Road North and South
When:   Monday, June 3 to Friday, June 7, 7:30 a.m to 2 p.m., and Friday, June 7, 7:30 a.m. to 2 p.m.
What:    Ramp narrows
Where:  From 1000' before Rudder Road bridge to the end of Rudder Road bridge
Why:     Bridge fence installation
 
Herndon Parkway East
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7, 9:30 a.m. to 2 p.m.
What:    Right lane closed
Where: From 1000 feet east of Van Buren Street to 800 feet west of Exchange Place
Why:     Material Delivery
 
Sunrise Valley Drive West
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7, 9:30 a.m. to 2 p.m.
What:    Right lane closed
Where: From Dulles Technology Drive to Dulles Station Blvd
Why:     Civil Work
 
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7 to Saturday, June 8, 9:30 a.m. to 2 p.m.
What:    Right lane closed
Where: From Thunder Chase Drive to Colts Brook Drive
Why:     Civil Work
 
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7 to Saturday, June 8, 9:30 a.m. to 2 p.m.
What:    Right lane closed
Where: From Reston Pkwy to 200' West of Edmund Halley Dr.
Why:     Civil Work
 
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7 to Saturday, June 8, 9:30 a.m. to 2 p.m.
What:    Right turn lane & Right lane closed
Where: Intersection of Sunrise Valley Drive and Reston Parkway
Why:     Civil Work
 
Sunset Hills Road East
When: Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7 to Saturday, June 8, 9:30 a.m. to 2 p.m.
What:    Alternating right and left lane closures
Where:  From 400 feet west of Town Center Pkwy to Bechtel Building Entrance
Why:     Civil work
 
Edmund Halley Drive North and South
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7 to Saturday, June 8, 9:30 a.m. to 2 p.m.
What:    Right shoulder closed
Where:  From Sunrise Valley Drive to 1000 feet north of Sunrise Valley Drive
Why:     Civil utility work
 
Moran Road South
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m.. and Friday, June 7 to Saturday, June 8, 9:30 a.m. to 2 p.m.
What:    Alternating left and right lane closures
Where:  From Moran Road to Old Ox Road
Why:     Civil work
 
Old Ox Road East and West
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m. and 10 p.m. to 4 a.m., Friday, June 7, 9:30 a.m. to 2 p.m. and 11 p.m. to 5 a.m., and Saturday, June 8 to Sunday, June 2, 11 p.m. to 5 a.m.
What:    Left lane closure
Where:  From 1000' east of Old Ox Road Bridge to the Dulles Greenway NB On-Ramp
Why:     Curb Repairs
 
When:   Monday, June 3 to Thursday, June 6, 9:30 a.m. to 3:30 p.m., and Friday, June 7, 9:30 a.m. to 2 p.m.
What:    Right lane closure
Where:  From 1000' east of Old Ox Road bridge to 1000' west of bridge
Why:     Curb Repairs
 
Lockridge Road North and South
When:   Monday, June 3 to Sunday, June 9, 12 a.m. to 11:59 p.m.
What:    Road closure
Where:  From Dulles North Transit Center Park & Ride to Prentice Drive
Why:     Civil work
 
Old Meadow Road - East

When: Monday, June 3, through, Thursday, June 6, 9 a.m. - 3:30 p.m., and Friday, June 7, 9 a.m. - 2 p.m.
What:   Right lane closure
Where: From Route 123 to Colshire Meadow Road
Why:    Utility relocation work

Route 123 - South
Monday, June 3, through, Thursday, June 6, 9 a.m. - 3:30 p.m., and Friday, June 7, 9 a.m. - 2 p.m.
What:    Left turn lane closure
Where:  From 200 feet before Old Meadow Road to Old Meadow Road
Why:     Utility relocation work

<><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.