Important Lane and Ramp Closures for the Week of March 13 – March 19

March 11, 2016
 
CONTACT:  Marcia McAllister
                    T: 703-572-0506
                    C: 571-730-9117
                    marcia.mcallister@dullesmetro.com
 
Important Lane and Ramp Closures for the
Week of March 13 - March 19
 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2.  Lane and shoulder closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Autopilot Drive, Rudder Road, Route 28, Sunrise Valley Drive and Sunset Hills Road during the week of March 13 - March 19.
 
All work is weather permitting.
 
See below for more detailed information. 
 
<><><> 
 
Dulles Toll Road (DTR) East
 
When:   Sunday, March 13 - Saturday, March 19, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.5 to 5.2 (from 1/10 mile past the Monroe Street overpass to between the Centreville Road and Reston Parkway overpasses)
Why:     Jack and bore operations
 
Dulles Toll Road (DTR) West
 
When:   Sunday, March 13 - Friday, March 18, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., Saturday, March 19, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.7 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass)
Why:     Jack and bore operations
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Monday, March 13 - Saturday, March 19, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., Saturday, March 19 - Sunday, March 20, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.7 to 3.3 (from 5/10 mile past the Route 28 overpass to 1/10 mile before the Monroe Street overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Monday, March 13 - Saturday, March 19, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., Saturday, March 19 - Sunday, March 20, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.3 (from 1/10 mile before the Monroe Street overpass to 1/10 mile past the Reston Parkway overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Sunday, March 13 - Saturday, March 19, 9 p.m. to 5 a.m.
What:    Eastbound lane reductions begin at 9 p.m.  Eastbound full lane closures begin at 10 p.m.  Road reopens at 5 a.m. Tuesday through Saturday mornings; road reopens at 11 a.m. on Sunday, March 13.  Follow detour.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Installation of a concrete span across the eastbound DIAAH. 
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Monday, March 14 - Sunday, March 20, 8 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.3 to 200 feet past the ramp to Copilot Way, including ramps in the vicinity (from 2/10 mile past the Rudder Road overpass to Saarinen Circle past Garage 1)
Why:    Road work
 
When:   Sunday, March 13 - Saturday, March 19, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Saturday, March 19 - Sunday, March 20, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Right lane closed
Where:  From mile marker 1.5 to 0.5 (from 3/10 mile before the Route 28 overpass to the Rudder Road overpass)
Why:    Construction entrance acceleration/deceleration lane
 
When:   Sunday, March 13 - Saturday, March 19, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., Saturday, March 19 - Sunday, March 20, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 2.5 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass)
Why:     Construction entrance acceleration/deceleration lane
 
Dulles Greenway East
 
When:   Monday, March 14 - Friday, March 18, 10 a.m. to 5 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why:     Road work
 
Dulles Greenway West
 
When:   Monday, March 14 - Friday, March 18, 6 a.m. to 3 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
Autopilot Drive
 
When:   Sunday, March 13 - Saturday, March 19, 9 p.m. to 5 a.m.
What:    Northbound lanes closed; northbound traffic diverted to one southbound lane.
Where:  Autopilot Drive from Rudder Road to Materials Road
Why:     Superstructures work
 
Rudder Road West
 
When:   Sunday, March 13 - Saturday, March 19, 9 p.m. to 2 a.m.
What:    Right lane closed
Where:  From the ramp from the westbound DIAAH to the Exxon Station
Why:     Jack and bore operations
 
Route 28 South
 
When:   Monday, March 14 - Thursday, March 17, 9:30 a.m. to 3:30 p.m., Friday, March 18, 9:30 a.m. to 12 p.m.
What:    Right lane closed
Where:  From the Dulles Toll Road overpass to the ramp to Frying Pan Road.
Why:     Electrical duct bank work
 
Route 28 North
 
When:   Sunday, March 13 - Monday, March 14, 10 p.m. to 5 a.m.
What:    Partial closure of Route 28 northbound ramp lanes to Dulles Toll Road
Where:  From beginning of ramp at Route 28 to split in ramp to DIAAH and DTR eastbound
Why:     Sign structure inspection
 
Sunset Hills Road East
 
When:   Monday, March 14 - Thursday, March 17, 9:30 a.m. to 3:30 p.m., Friday, March 18, 9:30 a.m. to 12 p.m.
What:    Right lane closed
Where:  Between the Fairfax County Parkway and Reston Parkway
Why:     Excavation
 
Sunrise Valley Drive West
 
When:   Monday, March 14 - Friday, March 18, 8:30 a.m. to 3:30 p.m.
What:    Right lane closed
Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to 550 feet past Dulles Station Boulevard
Why:     Construction Deliveries
 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.