Important Lane and Ramp Closures for the Week of May 1 - May 7

 

 

 

 

April 29, 2016
 
CONTACT:  Marcia McAllister
                    T: 703-572-0506
                    C: 571-730-9117
                    marcia.mcallister@dullesmetro.com
 
Important Lane and Ramp Closures for the
Week of May 1 - May 7
 
Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2.  Lane and shoulder closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Rudder Road, Dulles Greenway, Route 28, Sunrise Valley Drive and Sunset Hills Road during the week of May 1 - May 7.
 
All work is weather permitting.
 
See below for more detailed information. 
 
<><><> 
 
Dulles Toll Road (DTR) East
 
When:   Sunday, May 1 - Saturday, May 7, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 1.3 to 3.3 (from 1/10 mile past the Route 28 overpass to 1/10 mile before the Monroe Street overpass)
Why:     Jack and bore, duct bank work
 
When:   Sunday, May 1 - Saturday, May 7, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.2 (from 1/10 mile before the Monroe Street overpass to the Reston Parkway overpass)
Why:     Jack and bore operations
 
When:   Friday, April 29, 10 p.m. - Monday, May 2, 5 a.m.
What:    Two left lanes closed
Where:  From mile marker 3.2 to 5.0 (from 2/10 mile before the Monroe Street overpass to 2/10 mile before the Reston Parkway overpass)
Why:     Tower crane installation
 
Dulles Toll Road (DTR) West
 
When:   Sunday, May 1 - Saturday, May 7, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, May 7 - Sunday, May 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.7 (from 5/10 mile before the Reston Parkway overpass to 3/10 mile before the Monroe Street overpass)
Why:     Jack and bore operations
 
When:   Sunday, May 1 - Saturday, May 7, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m., and Saturday, May 7 - Sunday, May 8, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Left lane closed
Where:  From mile marker 3.5 to 1.5 (from 1/10 mile before the Monroe Street overpass to 3/10 mile before the Route 28 overpass)
Why:     Jack and bore operations
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Sunday, May 1 - Saturday, May 7, 9 p.m. to 5 a.m.
What:    Eastbound lane reductions begin at 9 p.m.  Eastbound full lane closures begin at 10 p.m.  Road reopens at 5 a.m. Follow detour.
Where:  From Saarinen Circle to mile marker 0.4 (near the Rudder Road overpass)
Why:     Installation of a concrete span across the eastbound DIAAH. 
 
When:   Sunday, May 1 - Saturday, May 7, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., and Saturday, May 7 - Sunday, May 8, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.0 to 2.3 (from Saarinen Circle to 2/10 mile before the Centreville Road overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Sunday, May 1 - Saturday, May 7, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m., and Saturday, May 7 - Sunday, May 8, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 5.4 (from 1/10 mile before the Monroe Street overpass to 2/10 mile past the Reston Parkway overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Friday, April 29, 10 p.m. - Monday, May 2, 5 a.m.
What:    Full closure of both eastbound DIAAH lanes
Where:  From mile marker 3.2 to 5.0 (from 2/10 mile before the Monroe Street overpass to 2/10 mile before the Reston Parkway overpass), all eastbound DIAAH traffic will be diverted to the left lane of the eastbound DTR and then redirected onto the DIAAH near the Reston Parkway overpass; follow detour. Drivers using the detour will NOT BE REQUIRED TO PAY A TOLL.
Why:     Tower crane installation
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Sunday, May 1 - Saturday, May 7, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, May 7 - Sunday, May 8, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.3 to 0.6 (from 1/10 mile after the Monroe Street overpass to 1/10 mile       before the Rudder Road overpass)
Why:    Duct bank work
 
When:   Sunday, May 1 - Saturday, May 6, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m., and Saturday, May 7 - Sunday, May 8, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.3 (from 5/10 mile before the Reston Parkway overpass to 1/10 mile past the Monroe Street overpass)
Why:     Road work
 
Rudder Road West
 
When:   Sunday, May 1 - Saturday, May 7, 9 a.m. to 2 p.m.
What:    Right lane closed
Where:  From the ramp from the westbound DIAAH to Ariane Way/Blue Lot access road
Why:     Duct bank work
 
Dulles Greenway East
 
When:   Monday, May 2 - Friday, May 6, 10 a.m. to 5 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why:     Road work
 
Dulles Greenway West
 
When:   Monday, May 2 - Friday, May 6, 6 a.m. to 3 p.m.
What:   Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.2 and 7.6 (from 2/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
Route 28 South
 
When:   Monday, May 2 - Thursday, May 5, 9:30 a.m. to 3:30 p.m., and Friday, May 6, 9:30 a.m. to 12 p.m.
What:    Right lane closed
Where:  From the Dulles Toll Road overpass to the ramp to Frying Pan Road.
Why:     Electrical duct bank work
 
Sunset Hills Road East
 
When:   Monday, May 2 - Thursday, May 5, 9:30 a.m. to 3:30 p.m., and Friday, May 6, 9:30 a.m. to 12 p.m.
What:    Right lane closed
Where:  Between the Fairfax County Parkway and Reston Parkway
Why:     Excavation
 
Sunrise Valley Drive West
 
When:   Monday, May 2 - Friday, May 6, 8:30 a.m. to 3:30 p.m.
What:    Right lane closed
Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to 550 feet past Dulles Station Boulevard
Why:     Construction Deliveries
 
                                                                    <><><><><>
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.