DULLES CORRIDOR METRORAIL PROJECT
Important Lane and Ramp Closures for the
Week of November 15 - 21 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2.  Lane and shoulder closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Rudder Road, Autopilot Drive, Centreville Road and Sunrise Valley Drive during the week of November 15 - 21. 
 
Crews will continue the bridge work at night over Centreville Road at the intersection of the entrance and exit ramps for the eastbound and westbound Dulles Toll Road (DTR). Drivers may experience minor delays due to lane closures in the northbound and southbound lanes between 10 p.m. and 5 a.m. 
 
See below for more detailed information.  
<><><> 
Dulles Toll Road (DTR) East
 
When:   Sunday, November 15 - Saturday, November 21, 10 p.m. to 5 a.m.
What:    Alternating double right and left lane closures of varying lengths
Where:  From mile marker 1.2 to 5.3 (from the Route 28 overpass to 1/10 mile past the Reston Parkway overpass)
Why:     Lane shifting
 
When:   Sunday, November 15 - Saturday, November 21, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.6 to 5.7 (from the overpass of the ramp to the northbound Dulles Greenway to 5/10 mile after the Reston Parkway overpass)
Why:     Jack and bore operations
 
When:   Sunday, November 15 - Saturday, November 21, 10 a.m. to 3 p.m.
What:    Ramp narrows, left and right side
Where:  Along the ramp to the eastbound DTR from southbound Route 28, and along the ramp from the eastbound DTR to northbound Route 28
Why:     Jack and bore operations
 
Dulles Toll Road (DTR) West
 
When:   Sunday, November 15 - Saturday, November 21, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 0.6 (from 5/10 mile before the Reston Parkway overpass to the overpass of the ramp to the northbound Dulles Greenway)
Why:     Jack and bore operations
 
When:   Sunday, November 15 - Saturday, November 21, 10 p.m. to 5 a.m.
What:    Alternating double right and left lane closures of varying lengths
Where:  From mile marker 5.3 to 1.2 (from 1/10 mile before the Reston Parkway overpass to the Route 28 overpass)
Why:     Lane shifting
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Sunday, November 15 - Saturday, November 21, midnight to 5 a.m.
What:    Full closure of eastbound lanes, traffic will be detoured to eastbound Aviation Drive then to new ramp to the eastbound DIAAH
Where:  From mile marker 0.0 to 0.4 (from Saarinen Circle to 1/10 mile before the Rudder Road overpass)
Why:     Aerial guideway construction
Police:  On site for safety
 
When:   Sunday, November 15, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
            Monday, November 16 - Friday, November 20, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
            Saturday, November 21, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.3 to 2.7 (from 2/10 mile before the Rudder Road overpass to 2/10 mile past the Centreville Road overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Sunday, November 15, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
            Monday, November 16 - Friday, November 20, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
            Saturday, November 21, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.2 to 5.7 (from 2/10 mile before the Monroe Street overpass to 5/10 mile after the Reston Parkway overpass)
Why:     Construction entrance acceleration/deceleration lane
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Sunday, November 15, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
            Monday, November 16 - Friday, November 20, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
            Saturday, November 21, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 2.7 to 0.3 (from 2/10 mile before the Centreville Road overpass to 2/10 mile past the Rudder Road overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Sunday, November 15, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
            Monday, November 16 - Friday, November 20, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
            Saturday, November 21, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.2 (from 5/10 mile before the Reston Parkway overpass to 2/10 mile after the Monroe Street overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Sunday, November 15, 8 a.m. to 2 p.m. and 10 p.m. to 5 a.m.
            Monday, November 16 - Friday, November 20, 8 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
Saturday, November 21, 10 p.m. to 8 a.m.
What:    Alternating right and left lane closures
Where:  From mile marker 0.3 to 200 feet past Copilot Way (from 2/10 mile after the Rudder Road overpass, continuing along Saarinen Circle past Daily Garage 1), including ramps in the vicinity of Daily Garage 1
Why:     Road widening
 
Dulles International Airport Access Highway (DIAAH)/Saarinen Circle West
 
When:   Tuesday, November 17 - Thursday, November 19, 9 p.m. to 5 a.m.
What:    Three right lanes closed
Where:  As the westbound DIAAH transitions to Saarinen Circle and continuing in front of Daily Garage 1, traffic will be reduced to a single left lane.  Stoppages of up to 20 minutes will occur after midnight. 
Why:     Overhead sign installation
Police:  On site for safety
 
Dulles Greenway East
 
When:   Monday, November 16 - Wednesday, November 20, 10 a.m. to 6 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why:     Road work
 
Dulles Greenway West
 
When:   Monday, November 16 - Friday, November 20, 3 a.m. to 3 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.0 and 7.6 (from 3/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
Autopilot Drive
 
When:   Sunday, November 15 - Saturday, November 21, 9 p.m. to 5 a.m.
What:    Full closure of northbound lanes
Where:  Northbound lanes of Autopilot Drive from Rudder Road to Materials Road closed;
northbound traffic will be shifted to the southbound lanes
Why:     Superstructures work
 
Rudder Road West
 
When:   Sunday, November 15, 9 a.m. to 2 p.m. and 10 p.m. to 5 a.m.
            Monday, November 16 - Friday, November 20, 9 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
            Saturday, November 21, 9 a.m. to 2 p.m. and 10 p.m. to 8 a.m.
What:    Right lane closed
Where:  Westbound Rudder Road from the ramp from the westbound DIAAH to the intersection with Ariane Way
Why:     Utility work
 
Centreville Road North and South
 
When:   Monday, November 16 - Saturday, November 21, 10 p.m. to 5 a.m.
What:    Left lane closures
Where:  Northbound and southbound Centreville Road between Woodland Park and Parcher Avenue.  Note:  Drivers may experience delays.
Why:     Overhead installation of floor and deck beams at the Centreville Road Bridge
 
Sunrise Valley Drive West
 
When:   Monday, November 16 - Thursday, November 19, 9:30 a.m. to 3:30 p.m.
            Friday, November 20, 9:30 a.m. to noon
What:    Right lane closed
Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to Dulles Station Boulevard
Why:     Construction Deliveries
 
<><><><><>
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2 construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.