Important Lane and Ramp Closures for the Week of November 2 – 7

November 2, 2015                                                                    

CONTACT: Marcia McAllister

                  T: 703-572-0506

                  C: 571-730-9117

                  marcia.mcallister@dullesmetro.com

 

DULLES CORRIDOR METRORAIL PROJECT
Important Lane and Ramp Closures for the
Week of November 2 - 7 
Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, lane shifting, utility work, excavation and other construction activities for the Metrorail Silver Line, Phase 2.  Lane and shoulder closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway, Rudder Road, Autopilot Drive, Centreville Road, Sunrise Valley Drive and Innovation Avenue during the week of November 2 - 7. 
 
Crews will continue the bridge work at night over Centreville Road at the intersection of the entrance and exit ramps for the eastbound and westbound Dulles Toll Road. Drivers may experience minor delays due to lane closures in the northbound and southbound lanes between 10 p.m. and 5 a.m. 
 
See below for more detailed information. 
 
<><><> 
Dulles Toll Road (DTR) East
 
When:   Monday, November 2 - Saturday, November 7, 10 p.m. to 5 a.m.
What:    Alternating double right and left lane closures of varying lengths
Where:  From mile marker 1.2 to 5.3 (from the Route 28 overpass to 1/10 mile past the Reston Parkway overpass)
Why:     Lane shifting
 
When:   Monday, November 2 - Saturday, November 7, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.6 to 5.7 (from the overpass of the ramp to the northbound Dulles Greenway to 5/10 mile after the Reston Parkway overpass)
Why:     Jack and bore operations
 
When:   Monday, November 2 - Saturday, November 7, 10 a.m. to 3 p.m.
What:    Ramp narrows, left and right side
Where:  Along the ramp to the eastbound DTR from southbound Route 28, and along the ramp from the eastbound DTR to northbound Route 28
Why:     Jack and bore operations
 
Dulles Toll Road (DTR) West
 
When:   Monday, November 2 - Saturday, November 7, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 0.6 (from 5/10 mile before the Reston Parkway overpass to the overpass of the ramp to the northbound Dulles Greenway)
Why:     Jack and bore operations
 
When:   Monday, November 2 - Saturday, November 7, 10 p.m. to 5 a.m.
What:    Alternating double right and left lane closures of varying lengths
Where:  From mile marker 5.3 to 1.2 (from 1/10 mile before the Reston Parkway overpass to the Route 28 overpass)
Why:     Lane shifting
 
Dulles International Airport Access Highway (DIAAH) East
 
When:   Monday, November 2 - Friday, November 6, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
            Saturday, November 7, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 0.3 to 2.7 (from 2/10 mile before the Rudder Road overpass to 2/10 mile past the Centreville Road overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Monday, November 2 - Friday, November 6, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
            Saturday, November 7, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 3.2 to 5.7 (from 2/10 mile before the Monroe Street overpass to 5/10 mile after the Reston Parkway overpass)
Why:     Construction entrance acceleration/deceleration lane
 
Dulles International Airport Access Highway (DIAAH) West
 
When:   Monday, November 2 - Friday, November 6, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
            Saturday, November 7, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 2.7 to 0.3 (from 2/10 mile before the Centreville Road overpass to 2/10 mile past the Rudder Road overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Monday, November 2 - Friday, November 6, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
            Saturday, November 7, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:    Alternating right and left lane closures of varying lengths
Where:  From mile marker 5.7 to 3.2 (from 5/10 mile before the Reston Parkway overpass to 2/10 mile after the Monroe Street overpass)
Why:     Construction entrance acceleration/deceleration lane
 
When:   Monday, November 2 - Friday, November 6, 8 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
Saturday, November 7, 10 p.m. to 8 a.m.
What:    Alternating right and left lane closures
Where:  From mile marker 0.3 to 200 feet past Copilot Way (from 2/10 mile after the Rudder Road overpass, continuing along Saarinen Circle past Daily Garage 1), including ramps in the vicinity of Daily Garage 1
Why:     Road widening
 
Dulles Greenway East
 
When:   Monday, November 2 - Wednesday, November 6, 10 a.m. to 6 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 7.6 and 12.2 (from Broadlands Boulevard to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why:     Road work
 
Dulles Greenway West
 
When:   Monday, November 2 - Friday, November 6, 5 a.m. to 3 p.m.
What:    Alternating right and left lane closures of varying lengths
Where:  Between mile marker 12.0 and 7.6 (from 3/10 mile after the mainline toll plaza to Broadlands Boulevard), short lane closures of varying lengths will occur
Why:     Road work
 
Autopilot Drive
 
When:   Monday, November 2 - Saturday, November 7, 9 p.m. to 5 a.m.
What:    Full closure of northbound lanes
Where:  Northbound lanes of Autopilot Drive from Rudder Road to Materials Road closed;
northbound traffic will be shifted to the southbound lanes
Why:     Superstructures work
 
Rudder Road West
 
When:   Monday, November 2 - Friday, November 6, 9 a.m. to 2 p.m. and 6 p.m. to 5 a.m.
            Saturday, November 7, 9 a.m. to 2 p.m. and 10 p.m. to 8 a.m.
What:    Right lane closed
Where:  Westbound Rudder Road from the ramp from the westbound DIAAH to the intersection with Ariane Way
Why:     Utility work
 
Centreville Road North and South
 
When:   Monday, November 2 - Saturday, November 7, 10 p.m. to 5 a.m.
What:    Alternating right and left lane closures
Where:  Northbound and southbound Centreville Road between Woodland Park and Parcher Avenue.  Note:  Drivers may experience delays.
Why:     Overhead installation of floor and deck beams at the Centreville Road Bridge
 
Innovation Avenue East
 
When:   Wednesday, November 4, 9:30 a.m. to 3:30 p.m.
What:    Right lane closed
Where:  Eastbound Innovation Avenue from Rock Hill Road to Greene Drive
Why:     Utility location
 
Sunrise Valley Drive West
 
When:   Monday, November 2 - Thursday, November 5, 9:30 a.m. to 3:30 p.m.
            Friday, November 6, 9:30 a.m. to noon
What:    Right lane closed
Where:  Westbound Sunrise Valley Drive from Dulles Technology Boulevard to Dulles Station Boulevard
Why:     Construction deliveries
 
<><><><><>
 
A 24/7 Hotline is available for Dulles Corridor Metrorail Project Phase 2 construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.