Important Lane and Ramp Closures for the Week of September 13 - September 19

September 11, 2015                                                                  

CONTACT: Marcia McAllister

                  T: 703-572-0506

                  C: 571-730-9117

                  marcia.mcallister@dullesmetro.com

Important Lane and Ramp Closures for the Week of September 13 - September 19

Phase 2 Barrier Installation, Utility Work, and Other Construction Activities Continue along the Dulles Toll Road, Dulles International Airport Access Highway, Dulles Greenway and Airport Roads.

Phase 2 Dulles Corridor Metrorail Project crews are continuing road widening, barrier installation, utility work, and other construction activities.  Lane and shoulder closures will occur along the Dulles Toll Road (DTR), Dulles International Airport Access Highway (DIAAH), Dulles Greenway and Rudder Road the week of September 13 – September 19.  See below for more detailed information.  

<><><> 

Dulles Toll Road (DTR) East

When:   Sunday, September 13 - Saturday, September 19, 10 a.m. to 3:30 p.m. and 8 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 0.6 to 5.7 (from the overpass of the ramp to the northbound Dulles

Greenway to 5/10 mile after the Reston Parkway overpass)

Why:     Jack and bore operations

 

When:   Sunday, September 13 - Friday, September 18, 10 a.m. to 3 p.m.

What:    Ramp narrows, left and right side

Where:  Along the ramp to the eastbound DTR from southbound Route 28, and along the ramp from the eastbound DTR to northbound Route 28

Why:     Jack and bore operations

Dulles Toll Road (DTR) West

When:   Sunday, September 13 - Saturday, September 19, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 5.7 to 0.6 (from 5/10 mile before the Reston Parkway overpass to the overpass of the ramp to the northbound Dulles Greenway)

Why:     Jack and bore operations

Dulles International Airport Access Highway (DIAAH) East

When:   Sunday, September 13, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.

            Monday, September 14 - Friday, September 18, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 3.2 to 5.7 (from 2/10 mile before the Monroe Street overpass to 5/10 mile after the Reston Parkway overpass)

Why:     Construction entrance acceleration/deceleration lane

 

When:   Sunday, September 13, 5 a.m. to 2 p.m. and 6 p.m. to 5 a.m.

            Monday, September 14 - Friday, September 18, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 0.3 to 2.7 (from 2/10 mile before the Rudder Road overpass to 2/10 mile past the Centreville Road overpass)

Why:     Construction entrance acceleration/deceleration lane

Dulles International Airport Access Highway (DIAAH) West

When:   Sunday, September 13, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.

            Monday, September 14 - Friday, September 18, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 2.7 to 0.3 (from 2/10 mile before the Centreville Road overpass to 2/10 mile past the Rudder Road overpass)

Why:     Construction entrance acceleration/deceleration lane

 

When:   Sunday, September 13, 5 a.m. to 2 p.m. and 7 p.m. to 5 a.m.

            Monday, September 14 - Friday, September 18, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.

What:    Alternating right and left lane closures of varying lengths

Where:  From mile marker 5.7 to 3.2 (from 5/10 mile before the Reston Parkway overpass to 2/10 mile after the Monroe Street overpass)

Why:     Construction entrance acceleration/deceleration lane

 

When:   Sunday, September 13, 8 a.m. to 2 p.m. and 10 p.m. to 5 a.m.

            Monday, September 14 - Friday, September 18, 8 a.m. to 2 p.m. and 6 p.m. to 5 a.m.

What:    Alternating right and left lane closures

Where:  From mile marker 0.3 to 200 feet past Copilot Way (from 2/10 mile after the Rudder Road overpass, continuing along Saarinen Circle past Daily Garage 1), including ramps in the vicinity of Daily Garage 1

Why:     Road widening

Dulles Greenway East

When:   Monday, September 14 - Friday, September 18, 10 a.m. to 5 p.m.

What:    Alternating right and left lane closures of varying lengths

Where:  Between mile marker 8.6 and 12.2 (from 1/10 mile after the Ashburn Village Boulevard overpass to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur

Why:     Road work

Dulles Greenway West

When:   Saturday, September 12, 6 a.m. to 3 p.m.

What:    Alternating right and left lane closures of varying lengths

Where:  Between mile marker 12.0 and 8.6 (from 3/10 mile after the mainline toll plaza to 1/10 mile before the Ashburn Village Boulevard overpass), short lane closures of varying lengths will occur

Why:     Road work

 

When:   Monday, September 14 - Friday, September 18, 6 a.m. to 3 p.m.

What:    Alternating right and left lane closures of varying lengths

Where:  Between mile marker 12.0 and 8.6 (from 3/10 mile after the mainline toll plaza to 1/10 mile before the Ashburn Village Boulevard overpass), short lane closures of varying lengths will occur

Why:     Road work

Rudder Road

When:   Sunday, September 13, 9 a.m. to 2 p.m. and 10 p.m. to 5 a.m.

            Monday, September 14 - Friday, September 18, 9 a.m. to 2 p.m. and 6 p.m. to 5 a.m.

What:    Right lane closed

Where:  Westbound Rudder Road from the ramp from the westbound DIAAH to the intersection with Ariane Way

Why:     Utility work

                                                                    <><><><><>

A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.