Large Off-Site Fill Material, Concrete Deliveries for the Week of May 16 - May 21

 

 

 

 

 
 
May 13, 2016 
 
CONTACT: Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
 
Large Off-Site Fill Material, Concrete Deliveries for the Week of May 16 - May 21
 
The following construction deliveries are scheduled May 16 - May 21 (Monday - Saturday), in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along U.S. Route 606 (Old Ox Road) and Mercure Circle as detailed below.
 
FILL MATERIAL
 
WHAT: Import fill material from off-site location (Reston Site). One hundred to 150 truckloads of fill material will be delivered to project site. The imported fill material will be used to replace unsuitable material that was found on the project site. All unsuitable material will remain on MWAA property and stockpiled. 
 
WHEN: Between the hours of 7 a.m. and 4 p.m.
 
HOW: Trucks will travel from the Reston Site via Reston Parkway (Rt. 602), Dulles Toll Road (Rt. 267), Old Ox Road (Rt. 606) and Mercure Circle. Return trip will be Old Ox Road (Rt. 606), Dulles Toll Road (Rt. 267) and Reston Parkway (Rt. 602). Roads will be cleaned during import fill operations by a sweeper truck.
 
CONCRETE
 
WHAT: Concrete delivery (18 trucks) for installation of Austin Sand Filter foundation.
WHEN: Monday, May 16 between the hours of 6 a.m. and 12 p.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site.
 
WHAT: Concrete delivery (seven trucks) and concrete pump truck for installation of Train
Hoist Mud Mats
WHEN: Thursday, May 19, between the hours of 6 a.m. and 11 a.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
 
WHAT: Concrete delivery (20 trucks) and concrete pump truck for installation of SIB
Basement Mud Mat
WHEN: Friday, May 20, between the hours of 6 a.m. and 12 p.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
 
<><><><><> 
A 24/7 Hotline is available for Phase 2 Rail Yard construction-related issues: 952-939-6690.  For general project information: www.dullesmetro.com or 703-572-0506.