Skip to main content
Silver Line on Track

Large Off-Site Fill Material, Concrete Deliveries for the Week of May 9 - May 14

 

 

 

 

May 6, 2016 
 
CONTACT: Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
Large Off-Site Fill Material, Concrete Deliveries for the 
Week of May 9 - May 14
 
The following construction deliveries are scheduled May 9 - May 14 (Monday - Saturday), in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along U.S. Route 606 (Old Ox Road) and Mercure Circle as detailed below.
 
FILL MATERIAL
 
WHAT: Import fill material from off-site location (Reston Site). One hundred to 150 truckloads of fill material will be delivered to project site. The imported fill material will be used to replace unsuitable material that was found on the project site. All unsuitable material will remain on MWAA property and stockpiled. 
 
WHEN: Between the hours of 7 a.m. and 4 p.m.
 
HOW: Trucks will travel from the Reston Site via Reston Parkway (Rt. 602), Dulles Toll Road (Rt. 267), Old Ox Road (Rt. 606) and Mercure Circle. Return trip will be Old Ox Road (Rt. 606), Dulles Toll Road (Rt. 267) and Reston Parkway (Rt. 602).
 
There will be a Loudoun County Sheriff's Office deputy parked at the project entrance to help maintain traffic flow and awareness of increased truck volume. Roads will be cleaned during operations by a sweeper truck.
 
CONCRETE
 
WHAT: Concrete delivery (19 trucks) for installation of Austin Sand Filter foundation.
 
WHEN: May 11 or May 12 between the hours of 6 a.m. and 11 a.m.
 
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site.
 
<><><><><> 
A 24/7 Hotline is available for Phase 2 Rail Yard construction-related issues: 952-939-6690.  For general project information: www.dullesmetro.com or 703-572-0506.