Skip to main content
Silver Line on Track

Large Off-Site Fill Material Importing for the Period of Feb. 29 - March 5

 

February 26, 2016 
CONTACT: Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
Large Off-Site Fill Material Deliveries for the Period of Feb. 29 - March 5
The following construction deliveries are scheduled Monday - Saturday, Feb. 29 - March 5, in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along U.S. Route 606 (Old Ox Road) and Mercure Circle as detailed below:
 
WHAT: Importing fill material from off-site location (Moorefield Site, Ashburn, VA). Eighty to 120 Truckloads of fill material will be delivered to project site. The imported fill material will be used to replace unsuitable material that was found on the project site. All unsuitable material will remain on MWAA property and stockpiled.
 
WHEN: Between the hours of 7:30 a.m. and 4 p.m.
 
HOW: Trucks will travel from the Moorefield Site in Ashburn via Ryan Road (Rt. 772), Belmont Ridge Road (Rt. 659), Evergreen Mills Road (Rt. 621) and Old Ox Road (Rt. 606). ALL TRUCKS WILL TURN RIGHT INTO AND OUT OF THE PROJECT SITE. Trucks will return to the Moorefield Site via Old Ox Road (Rt. 606), Greenway (Rt. 267), Loudoun County Pkwy and Ryan Road (Rt. 772). 
 
There will be a Loudoun County Sheriff's Office deputy parked at the project entrance to help maintain traffic flow and awareness of increased truck volume. Roads will be cleaned during operations by a sweeper truck.
 
 
<><><><><> 
A 24/7 Hotline is available for Phase 2 Rail Yard construction-related issues: 952-939-6690.  For general project information: www.dullesmetro.com or 703-572-0506.