Skip to main content
Silver Line on Track

Off-Site Fill Material, Concrete Deliveries for the Week of June 13 - June 18

  
June 13, 2016 
 
CONTACT: Marcia McAllister
            T: 703-572-0506
            C: 571-730-9117
Concrete Deliveries for the Week of June 13 - June 18
 
The following construction deliveries are scheduled June 13 - June 18 (Monday - Saturday), in support of the MWAA Rail Yard and Maintenance Facility project. The construction deliveries will be made to the Dulles Corridor Metrorail Project, Rail Yard and Maintenance Facility along U.S. Route 606 (Old Ox Road) and Mercure Circle as detailed below.
 
WHAT: Concrete delivery (8 trucks) and concrete pump truck for installation of the Deep Pit Mud Mats at the Service and Inspection Building.
WHEN: Tuesday, June 14, between the hours of 7 a.m. to 12 p.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Road (Rt. 606) to the project site.
 
 
WHAT: Concrete delivery (10 trucks) and concrete pump truck for installation of the Deep Pit Mud Mats at the Service and Inspection Building.
WHEN: Thursday, June 16, between the hours of 7 .m. and 12 p.m.
HOW: Trucks will travel from the Titan batch plant along Old Ox Rd/Rt. 606 to the
project site.
<><><><><> 
 
A 24/7 Hotline is available for Phase 2 Rail Yard construction-related issues: 952-939-6690.  For general project information: www.dullesmetro.com or 703-572-0506.