Important Lane and Ramp Closures for the 
Week of March 29 – April 4
 
Road/station work and inspections along Leesburg Pike (Route 7), Dolley Madison Boulevard (Route 123), Frontage Road, Tysons Boulevard, Dulles Toll Road (DTR) and the Dulles International Airport Access Highway (DIAAH) will continue the week of March 29, 2015 and will cause multiple lane closures.
 
Phase 2 Barrier Installation, Utility Work, and Other Construction Activities Continue along the Dulles Toll Road, Dulles International Airport Access Highway, Dulles Greenway, Airport Roads and Surrounding Roads.
 
Phase 2 Dulles Corridor Metrorail Project crews are continuing barrier installation, utility work, and other construction activities.  Lane and shoulder closures will occur along the Dulles Toll Road, Dulles International Airport Access Highway, Dulles Greenway, airport roads, and Route 28 the week of March 29 – April 4.  
 
This work will take place both overnights and during the daytime hours.  Please note that dates and times may change as lane closures can be adversely affected by inclement weather or other elements.  
 
<><><><><>
 
Please see the details for all of these activities as well as other lane, ramp and shoulder closures that have been approved for the week of March 29, 2015.  All closures are weather permitting and subject to change.  All night shift lane closures will have police escorts onsite for enhanced public safety.
 
Leesburg Pike (Route 7) East
 
When:  Monday, March 30 - Friday, April 2, 10 p.m. to 2 a.m.
Friday, April 3, 10:30 p.m. to 2 a.m.
What:   Right and center thru lanes of Route 7 eastbound closed
Where: From Spring Hill Road to Route 123 
Why:    Water valve & asphalt repairs
 
When:  Monday, March 30 - Friday, April 2, 10 p.m. to 2:00 a.m.
Friday, April 3, 10:30 p.m. to 2 a.m.
What:   Right and center thru lanes of Route 7 eastbound closed
Where: From Dulles Toll Road to Spring Hill Road
Why:    Water valve & asphalt repairs
 
Leesburg Pike (Route 7) West
 
When:  Monday, March 30 - Thursday April 2, 9:30 a.m. to 3:30 p.m.
Friday, April 3, 9:30 a.m. to 12 p.m.
What:   Right thru lane of Route 7 westbound closed
Where: From Westpark Drive to Spring Hill Road
Why:    Sidewalk repair punch list
 
When:   Monday, March 30 -Friday, April 2, 10 p.m. to 2 a.m.
Friday, April 3, 10:30 p.m. to 2 a.m.
What:   Right and center thru lanes of Route 7 westbound closed
Where: From Route 123 to Spring Hill Road 
Why:     Water valve & asphalt repairs
 
When:  Monday, March 30 - Thursday, April 2, 2 a.m. to 5 a.m.
Friday, March 27, 2 a.m. to 7 a.m.
What:   Right and center thru lanes of Route 7 westbound closed
Where: From Spring Hill Road to Dulles Toll Road
Why:    Water valve & asphalt repairs
 
Gosnell Road/Westpark Drive
 
When:  Monday, March 30 - Thursday, April 2, 10 p.m. to 5 a.m.
Friday, April 3, 10:30 p.m. to 7 a.m.
What:   Right thru lanes of Gosnell Road/Westpark Drive southbound closed
Where: From 200 feet north of Route 7 to 200 feet south of Route 7
Why:    Water valve & asphalt repairs
 
Frontage Road 
 
When:  Monday, March 30 - Thursday, April 2, 10:30 p.m. to 5 a.m.
Friday, April 3, 10:30 p.m. to 7 a.m.
What:   North and southbound alternating Frontage Road flagging operation
Where: From 600 feet east of Route 7 to 200 feet east of Route 7
Why:    Valve repair pavement patch
 
Dolley Madison Boulevard (Route 123) South
 
When:  Monday, March 30 - Friday, April 3, 10:30 p.m. to 2 a.m.
What:   Left and center thru lanes of Route 123 southbound closed
Where: From Scott Crossing Road to Capital One Drive
Why:    Punchlist work
 
When:   Monday, March 30 - Friday, April 3, 2 a.m. to 5 a.m.
What:    Right and center thru lanes of Route 123 southbound closed
Where:  From Scott Crossing Road to Capital One Drive
Why:     Punchlist work
 
Tysons Boulevard (East)
 
When:   Monday, March 30 - Thursday, April 2, 10:30 p.m. to 5 a.m.
Friday, April 3, 10:30 p.m. to 7 a.m.
What:   Right-most left turn lane of Tysons Boulevard eastbound to Route 123 northbound closed
Where: From Galleria Drive to Route 123
Why:    Water valve box repairs 
 
Dulles International Airport Access Highway (DIAAH) East
 
When:  Monday, March 30 - Friday, April 3, 9 a.m. to 3:30 p.m.
What:   Right shoulder of DIAAH eastbound closed
Where: From mile marker 5.8 to mile marker 6.0
Why:    Repairs at Crossover #6
 
When:  Monday, March 30 - Friday, April 3, 9 a.m. to 3:30 p.m.
What:   Right shoulder of DIAAH eastbound closed
Where: From mile marker 7.0 to mile marker 7.1
Why:    Repairs at Crossover #4
 
When:  Monday, March 30 - Friday, April 3, 9 a.m. to 3:30 p.m.
What:   Right shoulder of DIAAH eastbound closed
Where: From mile marker 8.3 to mile marker 8.4
Why:    Repairs at Crossover #3
 
When:  Monday, March 30 - Saturday, April 4, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths
Where: From mile marker 0.6 to 2.7 (from the Dulles Greenway ramp overpass to 2/10 mile past the Centreville Road overpass)
Why:    Construction entrance acceleration/deceleration lane
 
When:  Monday, March 30 - Saturday, April 4, 9 a.m. to 3:30 p.m. and 6 p.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths 
Where: From mile marker 3.2 to 5.4 (from 2/10 mile after the Monroe Street overpass to 2/10 mile before the Reston Parkway overpass)
Why:    Construction entrance acceleration/deceleration lane
 
Dulles International Airport Access Highway (DIAAH) West
 
When:  Monday, March 30 - Friday, April 3, 8 a.m. to 2 p.m.
What:   Right shoulder of DIAAH westbound closed
Where: From mile marker 8.6 to mile marker 8.5
Why:    Repairs at Crossover #2
 
When:  Monday, March 30 - Friday, April 3, 8 a.m. to 2 p.m.
What:   Right shoulder of DIAAH westbound closed
Where: From mile marker 7.1 to mile marker 7.0
Why:    Repairs at Crossover #4
 
When:  Monday, March 30 - Friday, April 3, 8 a.m. to 2 p.m.
What:   Right shoulder of DIAAH westbound closed
Where: From mile marker 5.8 to mile marker 5.6
Why:    Electrical inspections/repairs at Crossover #7
 
When:  Monday, March 30 - Saturday, April 4, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths
Where: From mile marker 2.7 to 0.6 (from 2/10 mile before the Centreville Road overpass to the Dulles Greenway ramp overpass)
Why:    Construction entrance acceleration/deceleration lane
 
When:  Monday, March 30 - Saturday, April 4, 8 a.m. to 2 p.m. and 8 p.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths 
Where: From mile marker 5.4 to 3.2 (from 2/10 mile before the Reston Parkway overpass to 2/10 mile after the Monroe Street overpass)
Why:    Construction entrance acceleration/deceleration lane
 
When:  Monday, March 30 - Saturday, April 4, 8 a.m. to 2 p.m. and 7 p.m. to 5 a.m.
What:   Alternating right and left lane closures
Where: From mile marker 0.3 to Copilot Way (from 2/10 mile after the Rudder Road overpass,
continuing along Saarinen Circle past Daily Garage 1)
Why:    Road work
 
Dulles Toll Road (DTR) East 
 
When:  Monday, March 30 - Friday, April 3, 10 a.m. to 3:30 p.m.
What:   Left shoulder of DTR eastbound closed
Where: From mile marker 8.3 to mile marker 8.4
Why:    Repair at Crossover #3
 
When:  Monday, March 30 - Friday, April 3, 10 a.m. to 3:30 p.m.
What:   Left shoulder of DTR eastbound closed
Where: From mile marker 7.0 to mile marker 7.1
Why:    Repairs at Crossover #4
 
When:  Monday, March 30 - Friday, April 3, 10 a.m. to 3:30 p.m.
What:   Left shoulder of DTR eastbound closed
Where: From mile marker 5.8 to mile marker 6.0
Why:    Repairs at Crossover #6
 
When:  Monday, March 30 - Saturday, April 4, 10 a.m. to 3:30 p.m. and 9 p.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths
Where: From mile marker 1.4 to 4.2 (from 2/10 mile past the Route 28 overpass to the Fairfax County Parkway overpass)
Why:    Jack and bore operations
 
Dulles Toll Road (DTR) West
 
When:  Monday, March 30 - Friday, April 3, 9:30 a.m. to 3:30 p.m.
What:   Left shoulder of DTR westbound closed
Where: From mile marker 8.6 to mile marker 8.5
Why:    Repairs at Crossover #2
 
When:  Monday, March 30 - Friday, April 3, 9:30 a.m. to 3:30 p.m.
What:   Left shoulder of DTR westbound closed
Where: From mile marker 7.1 to mile marker 7.0
Why:    Repairs at Crossover #5
 
When:  Monday, March 30 - Friday, April 3, 9:30 a.m. to 3:30 p.m.
What:   Left shoulder of DTR westbound closed
Where: From mile marker 5.8 to mile marker 5.6
Why:    Repairs at Crossover #7
 
When:  Monday, March 30 - Saturday, April 4, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
What:   Two left lanes closed
Where: From mile marker 2.9 to 1.4 (from 4/10 mile before the Centreville Road overpass to 2/10 mile before the Route 28 overpass)
Why:    Electrical duct bank work
 
When:  Monday, March 30 - Saturday, April 4, 9:30 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths
Where: From mile marker 4.2 to 1.4 (from the Fairfax County Parkway overpass to 2/10 mile before the Route 28 overpass)
Why:    Jack and bore operations
 
Dulles Greenway (East)
 
When:  Monday, March 30 - Friday, April 3, 10 a.m. to 5 a.m.
What:   Right lane closed
Where: Along the ramp from the eastbound Dulles Greenway to the eastbound Dulles Toll Road in the vicinity of mile marker 1.8 (just east of the mainline DTR toll booth)
Why:    Barrier installation
 
When:  Monday, March 30 - Friday, April 3, 10 a.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths
Where: Between mile marker 8.6 and 12.2 (from 1/10 mile after the Ashburn Village Boulevard
overpass to 2/10 mile before the mainline toll plaza), short lane closures of varying lengths will occur
Why:    Barrier installation, grading, paving
 
Dulles Greenway (West)
 
When:  Monday, March 30 - Friday, April 3, 5 a.m. to 3 p.m.
What:   Left lane closed
Where: Between mile marker 10.9 and 8.6 (from 1/10 mile after the Old Ox Road overpass to 1/10 mile before the Ashburn Village Boulevard overpass), short lane closures of varying lengths will occur
Why:    Barrier installation, grading, paving
 
Rudder Road
 
When:  Tuesday, March 31 - Friday, April 3, 9 a.m. to 4 p.m. and 6 p.m. to 5 a.m.
What:   Right shoulder closed
Where: Westbound Rudder Road from the Dulles Greenway ramp overpass in the vicinity of the southern end of the Green and Gold satellite parking lots
Why:    Construction entrance, install erosion and sediment controls
 
Autopilot Drive
 
When:  Monday, March 30 - Saturday, April 4, 9 p.m. to 5 a.m.
What:   Alternating right and left lane closures of varying lengths
Where: Northbound and Southbound Autopilot Drive from just north of the intersection of Rudder Road and Autopilot Drive to Cockpit Court.  Flaggers will be present at car rental parking lot entrances as needed and traffic flow will be maintained.
Why:    Utility relocation
 
Route 28
 
When:  Monday, March 30 - Friday, April 3, 9:30 a.m. to 3 p.m.
What:   Right lane and/or right shoulder closed 
Where: Southbound Route 28 along the ramp from the eastbound Dulles Toll Road
Why:    Construction entrance
 
When:  Monday, March 30 - Friday, April 3, 9:30 a.m. to 3 p.m.
What:   Ramp narrows (right side) 
Where: Southbound Route 28 along the exit ramp to Frying Pan Road
Why:    Construction entrance
 
<><><><><>
 
Access to all businesses in the construction areas along Routes 7 is maintained throughout the work periods. Motorists should stay alert, use extreme caution, and be prepared to allow extra time or alter their travel along these roads.
 
A 24/7 emergency hotline is available for Phase 2 Dulles Corridor Metrorail Project construction-related issues: 844-385-7245. For general project information: www.dullesmetro.com or 703-572-0506.