Lane Closures Planned Along Route 7 and I-66, Nov. 28-29

November 28, 2018
                                                                       
 
CONTACT:   Marcia McAllister
                     T: 703-572-0506
                     C: 571-730-9117
                     marcia.mcallister@dullesmetro.com
 
Lane Closures Planned Along Route 7 and I-66, Nov. 28-29
 
Lane and shoulder closures are planned Wednesday, Nov. 28, and Thursday, Nov. 29, along eastbound and westbound Route 7, and eastbound I-66 near the Silver Line Phase 1 alignment to permit construction crews to perform pipe repairs and underdrain work.
 
See below for more detailed information.  
 
Route 7 East
 
When:   Wednesday, Nov. 28 - Thursday, Nov. 29, 9:30 p.m. - 5 a.m.
What:    Left lane and right lane closures
Where:  From Route 267 ramp to Spring Hill Road 
Why:     Installing pipe repair bands and liners

Route 7 West
  
When:   Wednesday, Nov. 28 - Thursday, Nov.29, 9:30 p.m. - 5 a.m.
What:    Left lane and right lane closures
Where:  From Chain Bridge Road to Route 267 ramp
Why:     Installing pipe repair bands and liners
 
I-66 East
 
When:   Tuesday, Nov. 13 - Friday, Nov.16, 9:30 p.m. - 5 a.m.
What:    Inside left lane closure
Where:  From Route 267 (Dulles Connector Road) north ramp to Williamsburg Boulevard
Why:     Installing pipe repair bands and liners
 
 
All work is weather dependent and subject to change.
 
Signs and barrels will be used to help direct traffic and minimize impacts.  Drivers should use extreme caution in the areas and allow extra time to travel in these areas.
 
                                                                    <><><><><>
 